Parks Capital Projects
Meadowbrook Park Phase 1
Project Location
8025 Country Club Drive , Garner , NC 27529
Type of Project
Park Development
Current Project Stage
Design
Project Lead
Engineering
Project Description Design and construction of Phase 1 of Meadowbrook Park , which will feature walking trails and open spaces for recreation , a picnic shelter , and other amenities .
Purpose of Project Complete design and construction of Phase 1 of new regional park supported by the 2021 Parks and Recreational Bond . This development will activate as a public park a site that is listed in the National Register of Historic Properties for its role in African American cultural history of Wake County .
Project Funding Overview Total Project Cost Prior Year Expenditures Futures Year Costs $ 3,760,131 $ 0 $ 3,760,131
EXPENDITURES |
PRIOR YEAR FUNDING |
FY 2025 |
FY 2026 |
FY 2027 |
FY 2028 |
FY 2029 |
GRAND TOTAL |
Construction |
- |
- |
- |
- |
- |
$ 3,760,131 |
$ 3,760,131 |
Total |
- |
- |
- |
- |
- |
$ 3,760,131 |
$ 3,760,131 |
REVENUES |
PRIOR YEAR FUNDING |
FY 2025 |
FY 2026 |
FY 2027 |
FY 2028 |
FY 2029 |
GRAND TOTAL |
2021 Bonds |
- |
- |
- |
- |
- |
$ 3,760,131 |
$ 3,760,131 |
Total |
- |
- |
- |
- |
- |
$ 3,760,131 |
$ 3,760,131 |
211 5