To choose a system, we need to know the basic details of the application. ■ ■ What type of building assemblies is the joint formed by? - Floor/ ■ ■ What type of material is the building assembly? - Concrete, CMU, ■ ■ ■ ■ ■ ■ ■ ■ Floor, Floor/Wall, Wall/Wall, Top of Wall/Ceiling Gypsum What is the hourly rating you are looking for? - Assembly rating (1 – 4 hour) How big of a joint is required (inches) How much movement is required? - Must accommodate building movement (% of the joint size) Are there any special considerations? - Unique construction condition, environmental exposure NAVIGATING UL Example 1:- HW-D-0286 - Head of Wall First Two Alpha Characters – identify the type of joint system, barriers that form the joint. ■ ■ ■ ■ ■ ■ ■ ■ FF = Floor-to-Floor WW = Wall-to-Wall FW = Floor-to-Wall HW = Head-of-Wall 117