Projects
Bedewell School
Hebburn , South Tyneside Main Contractor : Carillion Building Tonnage : 215 Start : 19th September 2011 Finish : 14th October 2011
Central Walker Primary School
Newcastle Main Contractor : Sir Robert McAlpine Tonnage : 190 Start : 25th August 2011 Finish : 23rd September 2011
St Lawrence Academy
Scunthorpe Main Contractor : May Gurney Tonnage : 115 Start : 10th October 2011 Finish : 28th October 2011
Glendene School
Easington Main Contractor : Carillion Tonnage : 50t extension Start : 10th October 2011 Finish : 28th October 2011
Endike School
Hull Main Contractor : Sewell construction Tonnage : 230 Start : 17th October 2011 ( 6-week programme )
Tallent Automotive
Newton Aycliffe Main Contractor : Howard Russell Const Ltd Tonnage : 661 Start : 31st October 2011 Finish : End Nov 2011
St . George ’ s Academy
Sleaford and Ruskington Main Contractor : Balfour Beatty Construction Tonnage : 475 ( 4 phases ) Start : November 2011 Finish : Mid Nov 2011
Unipres factory , Sunderland
Main Contractor : Sir Robert McAlpine Client : Unipres Tonnage : 807 Start : 12th December 2011 Finish : April 2012
Pools on the Foreshore
South Shields Main Contractor : Graham Construction Ltd Tonnage : 385 Start : January 2012 Finish : March 2012
Finley Structures Ltd Quarterly Newsletter Issue 2 , October 2011