Step 2
Secure the First Tall Cabinet
2.1
Predrill a 3/16” hole at these marks, 1” up
from the bottom panel and 1” down from the top
panel.
1”
1”
2.2
Drive 2-1/2” x #8 fl athead screws into studs
at the predrilled areas.
2.3 Confi rm
that the Tall
Cabinet has not
been pulled out
of alignment or
twisted with the
fi rst attachment
screws.
Shim
Make any
adjustments
necessary prior
to progressing
with additional
attachments.