2020 COMPLETED PROJECTS
2020
2021
2022
* Street Improvements in conjunction with a Water / Sewer Renewal or Drainage Project
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
109th Street ( Ave E - Randol Mill ) Reclamation * 113th Street ( Randol Mill - Dalworth ) Reclamation * 113th Street ( Ave E - Dead End ) Reclamation * Abram Street ( Cooper - Collins ) Reconstruction
Altman Drive ( Center - East dead end ) Reclamation *
Avondale Court ( Thannisch - North dead end ) Reclamation * Collins Street ( Mayfield - IH20 ) Reconstruction Collins Street ( Park Row - Pioneer Parkway ) Reconstruction Cooper Street ( Abram - Main ) Reconstruction * Country Club Court ( Country Club - North dead end ) Reclamation *
Country Club Road ( Park Row - 3701 Country Club Road ) Reclamation *
E . Second Street ( Center - Mary ) Reconstruction Elm Street ( Third - Third ) Reconstruction Heatherbrook Drive ( 100 ' north of Latham Ct - 100 ' south of Latham Ct ) Reclamation * Hosack Street ( Center - Mary ) Reconstruction Kelly Terrace ( Collins - Park Row ) Reconstruction Kimberly Drive ( Sherry - Dead End ) Reconstruction
Lakehill Court ( North end of cul-de-sac - Approx . 2105 Lakehill Court ) Reclamation *
Latham Court ( Heatherbrook - East dead end ) Reclamation *
Mary Street ( Mitchel - Ray ) Reconstruction Mitchell Street ( Sunnyvale - New York ) Reclamation * Nichols Drive ( Orchard - Cooper ) Reclamation * Orchard Drive ( Randol Mill - Nichols ) Reclamation *
Park Row Drive ( Shady Valley - 100 ' east of Country Club ) Reclamation *
Pecan Street ( Abram - Main ) Reconstruction Ray Street ( Center - Mary ) Reconstruction
Redstone Drive ( Suffolk - 250 ' east of Suffolk ) Reclamation *
Roosevelt Street ( 230 ' north of Randol Mill - 450 ' north of Randol Mill ) Reclamation * Rose Street ( Mesquite - Mary ) Reconstruction
Sanford Street ( Collins - AT & T Way ) Heater Repaver Reclamation *
Suffolk Drive ( Wentworth - Redstone ) Reclamation * Summergrove Drive ( Tiverton - Summergrove ) Reclamation * Thannisch Drive ( Center - 1011 Thannisch ) Reclamation * Third Street ( Center - Elm ) Reconstruction Third Street ( Elm - Mary ) Reconstruction Vonner Court ( Thannisch - North dead end ) Reclamation * Weeks Ave ( Abram - Border ) Reconstruction
Quarters are based on calendar year .
CURRENTLY UNDER CONSTRUCTION
2020
2021
2022
* Street Improvements in conjunction with a Water / Sewer Renewal or Drainage Project
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
108th Street ( Ave H - North City Limits ) Reclamation * 111th Street ( Ave H - North City Limits ) Reclamation *
Avenue E ( SH 360 - Great Southwest Parkway ) Reconstruction Avenue H ( SH 360 - Great Southwest Parkway ) Reconstruction Calendar Road ( Curry - Harris ) Reconstruction Curry Road ( Calender - Calender ) Reconstruction Daniel Drive ( Cloudcroft - Mayfield ) Reconstruction Daniel Drive ( Mayfield - Green Hill ) Reconstruction Eden Road ( US 287 - Lions Gate ) Reconstruction Hanover Drive ( Natches - Windermere ) Reconstruction Harris Road ( Cooper - Calender ) Reconstruction Lincoln Drive / Van Buren Drive Intersection Surface Treatment Miriam Lane ( Hillcrest - Sherry ) Reconstruction Monticello Court ( Windsor - end of cul-de-sac ) Reclamation * Randol Mill Road ( Oakwood - 250 ' east of Oakwood ) Reclamation * Ryan Plaza Drive & Lamar Blvd Intersection - Surface Treatment
Vanderbilt Drive ( Hanover - Allen ) Reconstruction