CURRENTLY UNDER CONSTRUCTION
* Street Improvements in conjunction with a Water/Sewer Renewal or Drainage Project
109th Street (Ave E - Randol Mill) Reclamation*
CURRENTLY UNDER CONSTRUCTION
113th Street (Randol Mill - Dalworth) Reclamation*
* Street Improvements in conjunction with a Water/Sewer Renewal or Drainage Project
113th Street (Ave E - Dead End) Reclamation*
109th Street (Ave E - Randol Mill) Reclamation*
Abram Street (Cooper - Collins) Reconstruction
113th Street (Randol Mill - Dalworth) Reclamation*
Avondale Court (Thannisch - North dead end) Reclamation*
113th Street (Ave E - Dead End) Reclamation*
Belvedere Drive (Collins - Mitchell) Reconstruction
Abram Street (Cooper - Collins) Reconstruction
Cooper Street (Abram - Main)
Avondale Court (Thannisch - North dead end) Reclamation*
Davis Drive (UTA Blvd - Park Row) Reclamation*
Belvedere Drive (Collins - Mitchell) Reconstruction
E. Road to Six Flags Drive (Collins - Nolan Ryan Expressway) Reclamation*
Cooper Street (Abram - Main)
Grandview Drive (Oakwood - Greencove) Reclamation*
Davis Drive (UTA Blvd - Park Row) Reclamation*
Greencove Drive (Trailridge - Northridge) Reclamation*
E. Road to Six Flags Drive (Collins - Nolan Ryan Expressway) Reclamation*
Highpoint Drive (Cooper - Arbrook) Reclamation*
Grandview Drive (Oakwood - Greencove) Reclamation*
Inwood Drive (Collins - Daniel) Reconstruction
Greencove Drive (Trailridge - Northridge) Reclamation*
Mitchell Street (Sunnyvale - New York) Reclamation*
Highpoint Drive (Cooper - Arbrook) Reclamation*
New Haven Street (Skyline - E. Road to Six Flags) Reclamation*
Inwood Drive (Collins - Daniel) Reconstruction
Nichols Drive (Orchard - Cooper) Reclamation*
Mitchell Street (Sunnyvale - New York) Reclamation*
Northridge Drive (Oakwood - Greencove) Reclamation*
New Haven Street (Skyline - E. Road to Six Flags) Reclamation*
Oakwood Lane (Northridge - 2001 Oakwood) Reclamation
Nichols Drive (Orchard - Cooper) Reclamation*
Orchard Drive (Randol Mill - Nichols) Reclamation*
Northridge Drive (Oakwood - Greencove) Reclamation*
Pecan Street (Abram - Main) Reconstruction
Oakwood Lane (Northridge - 2001 Oakwood) Reclamation
Rayborn Drive (Biggs - Inwood) Reconstruction
Orchard Drive (Randol Mill - Nichols) Reclamation*
Southmoor Drive (Collins - Daniel) Reconstruction
Pecan Street (Abram - Main) Reconstruction
Suffolk Drive (Wentworth - Redstone) Reclamation*
Rayborn Drive (Biggs - Inwood) Reconstruction
Summergrove Drive (Tiverton - Summergrove) Reclamation*
Southmoor Drive (Collins - Daniel) Reconstruction
Texas Rangers Lot R Bridge
Suffolk Drive (Wentworth - Redstone) Reclamation*
Thannisch Drive (Center - 1011 Thannisch) Reclamation*
Summergrove Drive (Tiverton - Summergrove) Reclamation*
Timberlake Drive (East City limits - Park Row) Reclamation*
Texas Rangers Lot R Bridge
Timberlake Drive (Park Row - Pioneer) Reconstruction
Thannisch Drive (Center - 1011 Thannisch) Reclamation*
Vonner Court (Thannisch - North dead end) Reclamation*
Timberlake Drive (East City limits - Park Row) Reclamation*
Weeks Ave (Abram - Border) Reconstruction
Timberlake Drive (Park Row - Pioneer) Reconstruction
W. Second Street (Fielder - Davis) Sidewalks & Lightings
Vonner Court (Thannisch - North dead end) Reclamation*
Weeks Ave (Abram - Border) Reconstruction
W. Second Street (Fielder - Davis) Sidewalks & Lightings
Quarters are based on calendar year.
2018
2019
2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Quarters are based on calendar year.
2018
2019
2020
PROPOSED 2019 CONSTRUCTION
Design Phase
Quarters are based on calendar year.
2018
2019
2020
Right-of-way Phase
PROPOSED
2019 CONSTRUCTION
Construction Phase (includes franchised utility relocation)
Design Phase
* Street Improvements in conjunction with a Water/Sewer Renewal or Drainage Project
Right-of-way Phase
108th Street (Ave H - North City Limits) Reclamation*
Construction Phase (includes franchised utility relocation)
111th
Street (Ave H - North City Limits) Reclamation*
* Street Improvements in conjunction with a Water/Sewer Renewal or Drainage Project
Avenue H (SH 360 - Great Southwest Parkway) Reconstruction
108th Street (Ave H - North City Limits) Reclamation*
Calendar Road (Curry - Harris) Reconstruction
111th Street (Ave H - North City Limits) Reclamation*
Collins Street (Mayfield - IH20) Reconstruction
Avenue H (SH 360 - Great Southwest Parkway) Reconstruction
Collins Street (Park Row - Pioneer Parkway) Reconstruction
Calendar Road (Curry - Harris) Reconstruction
Curry Road (Caleder - Calender) Reconstruction
Collins Street (Mayfield - IH20) Reconstruction
E. Second Street (Center - Mary) Reconstruction
Collins Street (Park Row - Pioneer Parkway) Reconstruction
Eden Road (US 287 - Lions Gate) Reconstruction
Curry Road (Caleder - Calender) Reconstruction
Elm Street (Third - Third) Reconstruction
E. Second Street (Center - Mary) Reconstruction
Harris Road (Cooper - Calender) Reconstruction
Eden Road (US 287 - Lions Gate) Reconstruction
Hosack Street (Center - Mary) Reconstruction
Elm Street (Third - Third) Reconstruction
Kelly Terrace (Collins - Park Row) Reconstruction
Harris Road (Cooper - Calender) Reconstruction
Mary Street (Mitchel - Ray) Reconstruction
Hosack Street (Center - Mary) Reconstruction
Oak Street (Randol Mill - Cedar) Reclamation*
Kelly Terrace (Collins - Park Row) Reconstruction
Ray Street (Center - Mary) Reconstruction
Mary Street (Mitchel - Ray) Reconstruction
Rose Street (Mesquite - Mary) Reconstruction
Oak Street (Randol Mill - Cedar) Reclamation*
Tarpley Street (Main - Abram) Reclamation*
Ray Street (Center - Mary) Reconstruction
Third Street (Center - Elm) Reconstruction
Rose Street (Mesquite - Mary) Reconstruction
Third Street (Elm - Mary) Reconstruction
Tarpley Street (Main - Abram) Reclamation*
Third Street (Center - Elm) Reconstruction
Third Street (Elm - Mary) Reconstruction
4
Quarters are based on calendar year.
2018
2019
2020
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4