Enfield High Building Committee January 2017 Newsletter | Page 2
Enfield High School Building Committee Newsletter
Issue 4
The Fermi Wing
As you can see from the picture, the Fermi
Wing is coming close to completion. Starting
the first week of school, construction will
take place around the outside of the Fermi
Wing, including curbs, sidewalks, and
parking spaces for the next 6-8 weeks. The
interior finishes in the Fermi Wing continue
to make progress.
The EHS students will be transitioned into
the new Fermi Wing upon return from
Thanksgiving Break.
Gymnasium and Locker Rooms
The renovations of the gymnasium and both
the boys’ and girls’ locker rooms began in
June 2015. They will remain unavailable until
March, 2016. At that time they will be
reopened for use.
D Wing/A Wing/Front Lobby
All classes in the D Wing will be moved to
their permanent location in the Fermi Wing
as part of the thanksgiving break transition.
The demolition of the D Wing is scheduled
to start in December, 2015, after Fermi Wing
addition is complete. At the same time that
this work is occurring the construction on
the
current A wing and the Main Office
areas will begin. The renovations of
the A wing, Main Office and the new
lobby is currently scheduled to be
completed with the start of the 20162017 school year.
Music Addition/Auditorium
Renovation
addition which will house the band
and music programs will begin in
November, 2015. Renovations to
the auditorium will start in
January, 2016. The new Band wing
and the auditorium renovations
are currently scheduled to be
completed in January, 2017.
The construction of the music
Cafeteria Renovation
The cafeteria renovation is well underway,
and the expected completion date is
November 2015. The picture above is the
exterior of the new cafeteria.