New Ammonia Condensers - Import
CHALLENGE is part of our working philosophy
E-510 A/B are business critical equipment for Plant-2. Owing to the
severe fouling and leakage issues, re-designing and replacement of
these exchangers was proposed.
After technical evaluation and commercial negotiation New Exchangers
were ordered. The consignment left Italy on Feb 17, 2018 weighing approx.
110 Ton and reached Karachi on Mar 09, 2018. Special arrangements were
made in advance for its off-load and transportation on specialized multi
axle line vehicle.
In addition, substantial savings
were realized based on the
concessionary regime for duty & taxes. Consignment was safely
delivered and offloaded at Daharki site on March 16, 2018.
Moiz Ali
P&MM KPI’s Benchmarking
“ We are what we repeatedly do. Excellence, then, is not an act, but a habit.” (Aristotle)
At P&MM we believe in continuous learning and development of our people, processes and procedures. To
ensure the same, Aasim Butt, VP – P&MM, Admin & HSE, mandated the team to prepare a study in
collaboration with Hashtag Consulting, to benchmark divisional KPIs with international best Practices.
The study entailed primary research, one-on-one interviews with the team, focused group analysis,
& interviews with the line supervisors & Div. Head in order to evaluate end-to-end processes.
An exclusive workshop
was arranged in April, 2018
on Benchmarking & KPI
Study. A detailed S.W.O.T.
analysis
was
also
conducted whereby key
trade challenges & areas
for improvement were
identified.
Sadia Zahid
CO2 Recovery Unit - Import
RELOCATION - It’s going to be hard but HARD is not impossible
This unit is required to enhance capacity of Plant-2 for Gas utilization.
After technical due diligence and commercial negotiations,
Refurbished Unit E-300 Amine Plant 750 gpm was identified for
relocation from Canada.
After refurbishment the unit was transported from Alberta, Canada
to Port of Houston for its transportation to Karachi. Dedicated vessel
was booked from Houston to curtail long ocean transit time.
Refurbished items weighing approx. 125 Ton, reached Karachi on Feb
16, 2018. Special arrangements were made in advance for its off-load
and transportation. In addition, concessionary regime for duty /
taxes resulted in significant savings. Consignment was safely
delivered and offloaded at Daharki site on Feb 26, 2018.
Moiz Ali / Haider Isani