e-mosty December 2018 e-mosty December 2018 | Page 41

Figure 9: Blue gantry crane used to lift steel girders into place Figure 10: Complete Bridge Widening In the case of the pier crosshead beam, the problem was resolved by using the pre-stress to eliminate ten- sion at the connection. maintained either above deck, or removed for off-site maintenance. For the deck stitch, the solution was confined to only using existing reinforcement bars, and making them work optimally, which resulted in having to achieve a high fatigue classification for the welded connection between the stitch reinforcement and the existing cantilever bars. For the abutments, a shear only connection was suffi- cient, however the problem of differential settlement between the existing and new abutments had to be catered for. Where differential settlement was pre- dicted to be significant, dowelled bars in ducts were used, which were grouted when the full permanent load was reached. The integral nature of the final configuration meant that the original articulation would no longer suffice, as there would be two bearings with transverse re- straint on the same pier axis. VicRoads also took the opportunity to specify the replacement of the existing 20-year-old bearings as part of the contract. In addition, transverse seismic restraint blocks needed to be installed at each pier. The solution was to change the transverse restraint to occur at one of the new steel box girder bearings, while the longitudinal restraint remained at the three tall piers in the middle of the viaduct. Future maintenance access and durability were im- portant considerations in the design of the new struc- ture and upgrades. Efforts were made to ensure that new steel elements, such as the PSB, could largely be Although the new steel box girders are shielded by the concrete boxes either side and so are in a rela- tively benign environment, provision for future main- tenance was made by providing four access hanging points per section, at 2m intervals along the length of the structure. As this option caters for a variety of access platform formats and functions, including local and whole bridge maintenance, it was considered a better option for the future than designing a bespoke maintenance platform that would itself require maintenance and refurbishment in time. FORM OF CONTRACT Contract forms such as Alliance, Early Constructor Involvement, or Design Construct, all permit the De- signer to work with the Contractor from the early concept design stage to incorporate preferred con- struction methodology. This is highly advantageous, particularly when working with existing structures. For this project, the Design Construct contract created many challenges, such as the need to accurately de- termine strengthening requirements at tender stage. Several parts of the existing structure were approach- ing the limit where strengthening would be required. There is a large cost difference between strengthen- ing and not strengthening, which required the tender stage analysis to be extremely precise. 4/2018