e-mosty December 2017 MSS and Formwork Travellers | Page 46

Figure 5 + 6: Formwork travellers The construction of the main pylons is almost finished, while the segmental construction of the deck is in the early stages. The two first segments of each pier were cast in autumn 2017. The first segment of each pylon and of each side of the Atlantic Bridge has the special feature that it was cast using only the front part of the travellers. The front travellers were lifted with hydraulic jacks from the lifting structure and were fixed on the rear part to the deck and on the frontal part were hung from the lifting structure trough suspension bars. As a consequence, the front traveller works as a double supported structure during casting of the first segment. The next step is to move the front travellers down and to assemble the rear parts of the travellers on the ground. 4/2017 The lifting structures are launched and the complete traveller, that has a weight of 220tn, is hydraulically jacked into place. After the lifting of the complete form traveller the second segment is cast. From the second segment and the following, the complete form traveller is used to cast each segment. For each segment, the traveller is launched and then fixed on the previous concrete segment. Each segment is deliniated longitudinally by two laterals and one central precast diaphragm element. The traveller provides skidding rails and devices to move the precast elements to their position. The lateral precast diaphragm formwork was also designed and manufactured by RĂºbrica.