e-mosty 3/2016: Santiago Calatrava. Bridges Santiago Calatrava. Bridges. | Page 14

The bridge steel arch and deck segments were fabricated in Tampa, Florida by Tampa Steel Company and then transported by truck to the Dallas site. The first arch segments arrived on site in November 2014 (Figure 6). Ocelový oblouk a segmenty mostovky byly vyrobeny v Tampě na Floridě, společností Tampa Steel Company, a přepraveny na staveniště. První ocelové segmenty dorazily na stavbu v listopadu 2014 (obr. 6). Figure 6. Arrival of the first arch segment on site in November 2014 Erection of the Eastbound Bridge arch commenced in January 2015 and consisted of 11 separate lifts (Figures 7-10). The largest was the central segment which measured 312.5 feet long and weighed approximately 200 tons. This required a highly specialist winching operation by American Bridge Company and careful control of tolerances in lifting the element a height of approximately 275 feet to align snugly with the already positioned elements. Instalace oblouku východního mostu začala v lednu 2015. Vyzdvižení jeho segmentů spočívalo v 11 jednotlivých operacích (obr. 7 – 10). Největší byl středový segment s délkou 95 m a hmotností asi 200 tun. Vyžadovalo to vysoce specializovanou spolupráci s American Bridge Company a pečlivou kontrolu geometrie zdvihaných segmentů ve výšce cca 84 m a správné umístění k již instalovaným segmentům. Figure 7. Progress of the Eastbound Bridge arch erection, Figure 8. Installation of Eastbound Bridge arch segment. February 2015 3/2016