Draft GreenPoint Rated New Home Rating Manual, 2013 | Seite 92

M
Appliances and Lighting
VERIFICATION Measure M5.1 Field Verification: The Rater must complete field compliance verification, and take representative photos.
Documentation: The Rater must collect documentation specifying the efficacy of the lighting from the builder.
Measure M5.2
Documentation: The Rater must collect an Accountability Form from the lighting consultant or other appropriate expert, and the plan from the lighting consultant.
INTENT
To reduce energy consumption and energy costs associated with lighting. To contribute to environmental benefits, such as a reduction in greenhouse gas emissions.
M6. CENTRAL LAUNDRY
CRITERIA FOR QUALIFICATION This measure applies to multifamily only.
One point is available if the project includes a clothes washers and dryers in central areas that are accessible to all occupants. Do not install clothes washers and dryers in individual units.
VERIFICATION
Field Verification: The Rater will conduct field compliance verification and take photos of common laundry facilities.
INTENT Conserve water and foster a sense of community.
M7. GEARLESS ELEVATORS
CRITERIA FOR QUALIFICATION

DRAFT

This measure applies to multifamily only.
One point is available if the project includes a gearless( or gearless traction) elevators are used instead of hydraulic or geared traction systems in all locations.
DRAFT GreenPoint Rated New Home Rating Manual 86 Version 6.0, September 2013
© Build It Green