Selected : Year = FY2018-23 |
||||||
PIN Route / From-To Worktype / Cat Project Description |
6-Year Total Cost |
6-Year County Cost |
B-01473 |
Road Districts 2023 @ Various |
Road Districts Preservation |
Township Mortor Fuel Tax Projects |
Project Totals |
$ 540,000
$ 540,000
|
$ 0
$ 0
|
B-01141 |
Road Enhancements 2018 @ Various |
Enhancements Modernization |
Annual Joint Program of Roadside Enhancements
Project Totals
|
$ 100,000
$ 100,000
|
$ 100,000
$ 100,000
|
B-01291 |
Road Enhancements 2020 @ Various |
Enhancements Modernization |
Replace Plastic Markings |
Project Totals |
$ 100,000
$ 100,000
|
$ 100,000
$ 100,000
|
B-01427 |
Road Enhancements 2022 @ Various |
Enhancements Preservation |
Replace Plastic Markings |
Project Totals |
$ 100,000
$ 100,000
|
$ 100,000
$ 100,000
|
B-01192 |
Robert McClory Bike Path @ Scranton Ave . |
Bikepath Modernization |
Reconstruct Robert McClory Bike Path Bridge over Scranton Ave .
Project Totals
|
$ 62,500
$ 62,500
|
$ 62,500
$ 62,500
|
B-01450 |
Robert McClory Sewer @ Various |
Drainage Preservation |
Emergency sewer line repair on Robert McClory Bike Path
Project Totals
|
$ 247,000
$ 247,000
|
$ 247,000
$ 247,000
|
B-01373b |
Rollins Rd Culvert ( CR17 ) ( 2 of 2 ) @ Various |
Culverts Preservation |
Rollins Road 3000 Feet West of Fairfield Road
Project Totals
|
$ 575,000
$ 575,000
|
$ 575,000
$ 575,000
|
B-00731a |
Rollins Rd ( 1 of 3 ) @ CN RR @ IL Rte 83 |
Intersection Expansion |
Rollins Rd Gateway Improvement |
$ 3,211,900 |
$ 3,211,900 |
B-00731b |
Rollins Rd ( 2 of 3 ) @ CN RR @ IL Rte 83 |
Railroad Expansion |
Advance Utility Relocation Contract ComEd
Project Totals
|
$ 904,400
$ 4,116,300
|
$ 904,400
$ 4,116,300
|