DOT 2018 - 2023 Proposed Highway Improvement Program | Page 48

Summary Transportation Improvement Program - Carryforward Amounts Program Period : Fiscal Years 2018 to 2023 - Starting 12 / 1 / 2017
Selected : Year = FY2018-23
PIN Route / From-To Worktype / Cat Project Description
6-Year Total Cost
6-Year County Cost
B-01373a
Center St ( 1 of 2 ) @ Avon-Frmnt ditch
Culverts Preservation
Re-line Culvert
Project Totals
$ 17,100
$ 17,100
$ 17,100
$ 17,100
B-01074
Concrete Patch 2017 @ Various
Patch Preservation
Project Totals
$ 19,000
$ 19,000
$ 19,000
$ 19,000
B-01125
Concrete Patch 2018 @ Various
Patch Preservation
Project Totals
$ 103,900
$ 103,900
$ 103,900
$ 103,900
B-01223
Concrete Patch 2019 @ Various
Patch Preservation
Project Totals
$ 200,000
$ 200,000
$ 200,000
$ 200,000
B-01273
Concrete Patch 2020 @ Various
Patch Preservation
Project Totals
$ 210,000
$ 210,000
$ 210,000
$ 210,000
B-01326
Concrete Patch 2021 @ Various
Patch Preservation
Project Totals
$ 220,500
$ 220,500
$ 220,500
$ 220,500
B-01406
Concrete Patch 2022 @ Various
Patch Preservation
Project Totals
$ 231,500
$ 231,500
$ 231,500
$ 231,500
B-01457
Concrete Patch 2023 @ Various
Patch Preservation
Project Totals
$ 243,100
$ 243,100
$ 243,100
$ 243,100
B-00721
Conslt ROW Acq Litg Ast
Eng Support
Sales Tax Implementation Plan
$ 5,304,300
$ 5,304,300
Expansion
Project Totals
$ 5,304,300
$ 5,304,300
C :\ Users \ hd24311 \ Desktop \ cpms _ idot . FY1823 _ 5a ( sql export ). mdb - Ver . , 5 / 14 / 2018 3:21:58 PM
Page 7 of 42