Division Corridor Strategy Final Report Division-Corridor-Strategy-Final-Report | страница 82
As with the sidewalk improvements, each of the
access management improvement approaches listed
above should be considered in conjunc on with the
adjacent re-development ini a ves on a block by
block basis or as a group of blocks, as appropriate for
the treatment.
U lity Assessment
Bury the u lity lines and removal of the u lity
poles along Division Street is recommended as a
long-term eff ort with the understanding that there
are signifi cant costs and right-of-way challenges.
This ac on had overwhelming support during this
planning process by the public, land owners, and the
DCAC. The planning team observed approximately
80 u lity poles along Division Street. The poles are
visually distrac ng, hinder redevelopment oppor-
tuni es, force pedestrians to enter the roadway to
maneuver around them, and are located in areas
desired for future sidewalks and ramps. All these
issues were iden fi ed during this process and are
well documented as challenges in previous reports
and studies. However, no ac ons have been imple-
mented to date. This is most likely due to challenges
associated with cost and right-of-way acquisi ons.
sion and provided three op ons for considera on: 1)
burial, 2) consolida on, and 3) reloca on. It should
be noted that Oncor owns most u lity poles within
the Corridor and other franchise providers use the
poles and would likely follow Oncor’s direc on.
Op on 1- Burial: This is the most desired and best
long-term solu on to address public and stakeholder
desires. However, this is a signifi cant cost and,
by nature, would require an approximate 10 foot
easement along the fronts of proper es adjacent
to Division Street. This scenario is illustrated in The
City of Arlington’s Downtown Master Plan. The
easement will pose very diffi cult site design situa-
ons for many businesses and in some cases, require
structure removal or loss of sales space. This op on
would also involve upgraded u lity systems to meet
code requirements, a cost some property owners
commented would be too much of a fi nancial
burden. Burial may be the best op on to consider as
redevelopment projects materialize.
Op on 2- Consolida on: This op on recognizes
many poles could be removed that are not
necessary. In addi on, overhead lines could be
consolidated and moved to the south side of Division
Street. This would aid in reducing the amount of
visual clu er and pedestrian obstacles. Consolida-
opera on and safety.
• Parking access directly off of Division Street
should be gradually eliminated as redevelop-
ment takes place along the Corridor.
• Parking management for the Division Street
Corridor should encourage collec ve parking
for each block, with access to the parking from
the side streets to replace numerous ineffi cient
small parking areas along the street frontage
and to make its use more eff ec ve.
• Raised medians should be provided, in concert
with the managed property access and parking
to enhance the safety and opera on of Division
Street.
Findings and Op ons
During this p rocess, the planning team met with the
u lity companies as part of the stakeholder meet-
ings. The planning team outlined past plans and
desires and discussed current project goals. The
u lity company representa ves were open to discus-
Utility poles and overhead powerlines within the
study area.
Division Street Corridor Strategy
City of Arlington
69