times for the bracket in Problem 14.8. The
unit is to be prepared in week 10. The lead
times for the components are bracket (1
week), base (1 week), spring (1 week), clamp
(1 week), housing (2 weeks), handle (1 week),
casting (3 weeks), bearing (1 week), and shaft
(1 week). a) Prepare the time-phased product
structure for the bracket. b) In what week do
you need to start the castings?
Chapter 14, problems 14.13