Killunaght Rd ( Zone E ) along with BT ducting at Foreglen Rd ( Zone E ) and Claudy ( Zone D ). Landscaping is ongoing throughout the site , mostly tree and hedgerow planting and line markings to the new dual carriageway have started throughout the scheme .
Structure 01 Substantially complete and being used by traffic
Structure 02 Waterproofing ongoing and preparing for verge infill and surfacing to start February 2022 .
Structure 03 Northern wingwalls poured mid-January , parapet beams and parapet rails installed by the end of January 2022 .
Structure 04 Substantially complete and being used by traffic
Structure 05A Substantially complete and being used by traffic
Structure 05B Pouring restraining slabs end of January 2022 . Waterproofing ,
kerb and verge infill competition date approx . March and preparing for surfacing Mid-March 2022 .
Structure 07 Waterproofing completed mid- January and installation of kerbs , ducting and verge to be completed Mid-February . Surfacing to commence March 2022 .
Structure 08 Waterproofing completed mid- December , kerbs ducting and verge infill to be completed end of February and preparing for initial surfacing end of February 2022 .
Structure 09 Substantially complete being used by traffic
Structure 10 Piling works completed by the end of January and retaining walls to be completed March 2022 .
Structure 11 Substantially complete
Structure 12 Substantially complete