34
Cut and fill operations are substantially complete with excavation works ongoing at Tamnaherin ( Zone A ) along with pond excavation works at Foreglen ( Zone E ). Mainline drainage outfall works at ponds is ongoing at Burntollet ( Zone B ) and Killunaght Rd ( Zone E ).
Further works to access tracks are continuing at Gortilea ( Zone D ) along with concreting of lanes and drainage works ongoing . Side roads are ongoing at various locations at Dungiven ( Zone F ) Tamnaherin junction , Ardmore and Fawney Rd ( Zone A ) Claudy junction ( Zone D ) and accommodation works are ongoing at Baranailt ( Zone C ) Dungiven ( Zone F ) and Tamnaherin Rd ( Zone A ).
Pavement operations are ongoing along with surfacing works between Claudy ( Zone D ) and Feeny Rd ( Zone E ). Fencing is ongoing between Gulf and Claudy ( Zone C ) west of Feeny Rd ( Zone E ) and Tamnaherin ( Zone A ) will follow in the coming weeks .
NIW diversions and new installations are underway at Claudy Junction ( Zone D ) Ardmore Rd ( Zone A ) and
www . constructionviewonline . co . uk