COWES PORT HANDBOOK 2014 - 2015 Stage 4 - The next stage involves the installation of the gravel pre-load up to approximately 5.5m above chart datum using the same trailer hopper dredger, floating pipeline and spraying barge as was used for the sand layer. See Figures 2 & 4. When the crest levels reach around Mean High Water, the spraying pontoon will be utilised spraying gravel against the slopes of the breakwater. Excavators will be utilised to shape the breakwater and Boskalis Westminster retrieve gravel outside of the intended profile. Fig 3. Stitcher and barge A nine month consolidation process will then follow over the autumn and winter of 2014-2015, to allow for settlement of the gravel core. It must be emphasised that the breakwater will resemble a gravel spit during the winter of 2014/15 and will only begin to take its final finished appearance during the 2015 works. Boskalis Westminster Fig 4. Dredger, pipeline and spraying pontoon 2015 Breakwater Construction Programme .......................................................... The second phase of construction will start towards the spring or summer of 2015 when the sand and gravel layer will be re-dressed up to 5.9m. This will then be followed by the placement of rock armour on the breakwater to give the protection and finished appearance. Excavators will reshape the breakwater to its final profile and fixed aids to navigation will be placed on the breakwater. For all the latest news, safety and navigational information regarding the construction of the detached breakwater in Cowes, please go to www.cowesharbourcommission.co.uk and check the latest Local Notices to Mariners. COWES.co.uk 25