SCREENED REAR PORCH 1.3
ANY CHANGE TO THE OUTSIDE OF THE HOME REQUIRES BOTH NARC AND ACC APPROVAL
1. Obtain an application form from Kings Ridge Management Office (CMO) located at the
clubhouse. Submit the application form with a copy of the guideline, plat plan, the product
data with specifications, and any other pertinent information. Return your completed
application to the CMO. Call 811 prior to the start of any construction.
2. Do not start construction or any improvement, alteration, or addition to any existing
structure or make any site improvements or changes prior to approval. After approval by
the ACC, obtain and pay for all permits that may be required by governmental authorities.
Upon completion submit copies of all permits to the CMO for filing with your Architectural
Application.
3. Proposed work to add screens to a rear porch shall commence within 45 days of approval
by the ACC and shall be completed within 180 days of commencement. Time extensions
may be granted by the NARC upon written request.
4. Framing shall be aluminum, painted white. Screening shall be 18x18 or 18x14 mesh dark
gray or charcoal color. Screen appliqués are permitted: See guideline 1.5.1 #3.
5. Screen panels may be supplied with an aluminum kick plate, maximum 16 inches high above
floor line. One door is required and its design shall be compatible with screened addition
design. Replacing screens does not require ACC approval.
6. Homeowner shall control the work and conduct of all contractors on the site.
7. Immediately remedy any damage to the site and adjacent premises caused by any
contractor or worker. Failure to take such action in a timely manner will be cause for the
neighborhood association to correct said damage at homeowner’s expense.
Neither the Kings Ridge Community Association, Inc. nor the neighborhood association shall
have or shall assume any responsibility for maintenance or warranty for the screen work and
modifications to the existing home and site.
End of Guideline 1.3
Approved by the Board of Directors April 26, 2017
Effective April 26, 2017