Cold Link Africa September/October 2017 | Page 45

PROJECT INCORPORATING COLD CHAIN the end of February 2017 and were awarded the job by the end of March. They were on site within 10 days and completed the entire upgrade in only two and a half months. It was crucial that the upgrade would be complete by the end of May 2017, as FPT had signed a contract and was getting extra product in. CATERING FOR A COLD TREATMENT MARKET One of the new HC blowers installed in the upgraded chambers. The result of the modified suction accumulator vessel as per MRE’s modifications. CLIENT BRIEF The client knew exactly what they wanted on this project. MRE had a service contract with FPT for the existing plant room. Thus, MRE was the preferred choice when it came to handling the upgrade. FPT simply specified how many cold rooms they wanted to cool and the temperature they required — the rest was up to MRE. MRE’s Dennis van der Westhuizen designed the system and Gershwin Cornelius coordinated the project on site, ensuring everything went according to plan. Citrus pallets in the upgraded chambers on the first floor EXPANDING THE PLANT The installation comprised upgrades and extensions to the existing plant room while also upgrading the five cold stores. This project included the supply, delivery, installation, and commissioning of refrigeration equipment and piping to the plant room and five cold stores. The upgrade included the following capital equipment and modifications: • A previously used Sullair C20 screw compressor coupled with a 225kW Siemens motor was installed to operate at -10°C suction temperature and +35°C condensing temperature. • An existing suction accumulator has been modified to suit the upgrade of the five controlled cold chambers. • Ten stainless steel coolers have been installed with new valve stations. • Each stainless steel/aluminium cooler has been supplied with three AMS fans with airflow of 3.1m 3 /s. TIGHT DEADLINE The team worked under extreme pressure with very tight deadlines. MRE quoted by With the added chambers in place, FPT’s entire operation runs more smoothly. The pallets are first inspected according to the stringent US regulations and then taken to cold chambers on the ground floor. As the US is a cold treatment market, this means the pallets must be under cold treatment pre-cooling conditions for 72 hours before they can be loaded on the vessel. Oranges are normally shipped at 3.5°C, but not for the cold treatment programme. Product comes in at ambient temperature and is then cooled to -0.6°C. For the last 24 hours of the 72-hour pull- down, it is crucial that the product maintains that temperature. There must not be any deviation or the cold treatment cycle will have to start over. All the cold treatment cooling is done on the ground-floor chambers, but when the ground-floor chambers are full, the excess pallets for a specific vessel can be taken to the first floor and kept under cooling until space becomes available. Once the pallets have been inspected for the first vessel, the producers bring in more pallets for the second vessel. These will also go up to the first floor. FPT can now store 4 600 pallets in the ground-floor chambers and a further 1 500 in the first-floor chambers. The product arrives from