Cold Link Africa October 2019 | Page 42

FEATURE INCORPORATING COLD CHAIN of the various parties to the agreement after termination and these remain in force after termination by contractual stipulation. In terms of clause 38.3, these provisions are listed under sub-clauses 38.5.1 to 38.5.9 and are dealt with individually under the bulleted headings hereunder. Neither party can force the other to continue the N/S works after termination. It is submitted that, unless the subcontractor is adamantly opposed to completing the N/S works, it is normally in the innocent employer’s interests to try to negotiate a continuation rather than a final parting. Although not always practically accessible (for example, with liquidity issues), the employer who is not in default potentially has a claim for damages to the extent that extra costs are reasonably incurred. Aside from the common law obligation to mitigate damages, an employer also normally has a very keen interest in avoiding delays and excessive costs because of practical limitations on funds available to it and the need for the investment to be financially active and viable. An astute subcontractor is able to gauge through negotiations with the employer, the tipping point where the latter will find the benefits of retaining the subcontractor’s services are outweighed by the burden of the subcontractor’s terms for completion of the N/S works. All parties have access to urgent interdicts to enforce their immediate rights and should use them without procrastination in the event of any threat to their rights. POSSESSION, RESERVATION OF OWNERSHIP AND LIENS It is not uncommon for the employer to issue notice of termination and then to have its security personnel occupy the site and evict all persons from the site shortly after. It is this latter action that may embarrass the employer. The installation of its own security on site is not necessarily an illegal action as, on termination, the employer acquires certain rights such as those in terms of PBA clause 36.5.5 ‘The employer may employ other parties to safeguard the works, complete the outstanding work …” and PBA clause 36.5.6 ‘The employer may use the contractor’s materials… plant… machinery’ which means that the employer is contractually entitled to secure the works on termination and to take over and use materials, plant and machinery that are on site to complete the works. The danger to the employer, if it takes over the site aggressively and evicts the contractor, is that it could be seen as taking the law into its own hands 2 and a spoliation order could be available to the contractor in such cases. Per Gorven J at paragraph 4 in Taddese and others v Peer NO and others (5250/2016) [2016] ZAKZDHC 26 (4 August 2016), quoting in turn from Ivanov v North West Gambling Board & others 2012 (6) SA 67 (SCA) para 19 and based on Voet 41.2.16: ‘There are only two requirements for spoliatory relief; that the applicants were in peaceful and undisturbed possession of the disputed premises and that they were deprived of that possession without consent or recourse to law. The fact that the applicants’ possession is wrongful or illegal is irrelevant. The underlying rationale is that persons should not take the law into their own hands. If these two requirements are proved, possession is restored without any enquiry being made into the legal rights of the parties to possession.’ It is submitted that the employer should act decisively in accordance with the terms on which it relies but take great care to avoid any unreasonable force in carrying out its actions so as not to run afoul of these legal principles. If there are potential liens it should ensure they are noted by the principal agent and respected and dealt with to avoid conduct that could also constitute dispossession. It should particularly not prevent reasonable access for senior staff who may need to be involved in assessing the work status report and final account matters and should also not be seen to be taking over any goods of which it is not entitled to take over control or possession. The subcontractor has similar rights which are equally enforceable, but it may have to found and enforce them differently and should seek legal advice as it would have difficulty proving peaceful and undisturbed possession of a site 3 . The right to the enforcement of a lien by a subcontractor is only available through a claim for compensation which it secures. The subcontractor should distinguish between its right to ownership of materials not ‘delivered’ to the employer in terms of the applicable common law and the contract (which is, any reservation of ownership it may be entitled to enforce) and a debtor’s lien it may have over goods. The latter requires that the lien protects a sum which is already due and payable. The need for the subcontractor to have well-marked lockable stores for its materials 4 and stickers on any definable and detachable goods such as plant, buildings and independent structures, should be evident from these considerations. In the case of an employer with a legitimate complaint and with honourable intentions there is a degree of benefit if it acts decisively in that all evidence and work is protected. However, where an employer is intent on protecting its own patrimonial interests at all costs, it may well result in the dispossession of the subcontractors’ property and an attempt to alienate its liens leaving it to the subcontractor to attempt to recover revenue from the contractor (see also the Buzzard Electrical vs 158 Jan Smuts Avenue Investments and other 1996 (4) SA 19 (A), which found that the subcontractor has no enrichment claims against the employer). In such cases the establishment of liens and rights of ownership on materials delivered but not yet paid is important and immediate employment of experienced legal practitioners, preferably before the termination is implemented, becomes very important in addition to the enforcement of the NSSA provisions. GUARANTEES AND SECURITY Although a discussion of the subcontractor’s liability in terms of its guarantees falls outside the scope of this article, a brief mention is appropriate. 1. With regards to payment guarantee by the contractor to the subcontractor (which is an on-demand guarantee), the existing guarantees, in terms of their own provisions, remain in force until the earlier of: b. the settlement of the final payment advice in terms of the Agreement; or c. on payment in full of the Guaranteed Sum; or d. the Guarantee expiry date. This last option is particularly important because it is not uncommon for the guarantor to seek to insert such a date on the basis of the construction programme. Whilst the contract is in process, there are 2. 3. 4. When a principal building agreement is terminated, the effect cascades down to numerous subcontractors and suppliers who are most often actually the ultimate risk bearers on behalf of the contractor. 42 www.coldlinkafrica.co.za 5. remedies available to enforce renewal of the guarantee when it expires before the issue of the final payment advice but, after termination there is little a subcontractor can do and for this reason the insertion of an expiry date should be carefully weighed against the effect of and possibility of termination. 2. With regards to the subcontractor’s construction guarantee which at clause 11 specifically provides only for expiry: a. in terms of clauses 1.1.4 (issue of the final payment advice for variable guarantees); or b. clause 2.1 (the last certificate of practical completion for fixed guarantees with cash retention until final payment advice); or c. in terms of clause 14.7.1 (cash retention sum reducing after the issue of the final payment advice). Therefore, the construction guarantee or cash retention remains in force until the issue of the Final Payment Advice unless a specific expiry date supervenes. It is submitted that, where no call is made on a construction guarantee, its value would be as applicable at the date of termination. Payment by the guarantor is inter alia dependent on the contractor’s bare allegation of either: a. a failure to make payment to the contractor in terms of a payment advice statement (which is issued by the contractor); or b. termination of the subcontract due to the subcontractor’s default. Both these averments are entirely in the contractor’s control and the guarantor is not able to contest the release of the sum on the basis of any dispute as to the correctness of the contractor’s averment because such a dispute falls outside the terms of the guarantee and only within the provisions of the N/S agreement which are not part of the guarantee. A subcontractor terminating in terms of clause 38.3 could find itself unable to oppose the contractor’s collection of the sum guaranteed and should ensure it has considered this possibility, especially where insolvency of the contractor has supervened and the liquidator is trying to augment the funds available to it 5 . The advance payment guarantee, which is a guarantee between the subcontractor and the employer, is dealt with in terms of clause 38.5.8 (to be discussed in the next article). *Note: this is not a legal opinion and no liability for reliance on its contents attaches to the writer or sender. To be continued in an upcoming edition of Cold Link Africa. CLA ‘It is a fundamental principle that no man is allowed to take the law into his own hands; no one is permitted to dispossess another forcibly or wrongfully and against his consent of the possession of property, whether movable or immovable. If he does so, the Court will summarily restore the status quo ante, and will do that as a preliminary to any inquiry or investigation into the merits of the dispute.’ (Nino Bonino v De Lange 1906 TS 120 at 122) The legal definition of this term falls outside the scope of this article. Breaking a lock and entering a store as well as removing stickers are examples of taking the law into one’s hands and subject to challenge. There is a great need for the provisions of the JBCC construction guarantee to be reviewed but in the meantime subcontractors need to consider making provision in the wording for a requirement for a reciprocal payment guarantee in the same amount as the claim against the construction guarantee where dispute resolution procedures have been initiated to contest the validity of the claim. COLD LINK AFRICA • OCTOBER 2019