Cold Link Africa May/June 2016 Vol 1 No 5 | Página 36

PROJECT INCORPORATING COLD CHAIN Continued from Page 1 Inside the new state-of-the-art Imperial Cold Logistics complex I mperial Cold Logistics had outgrown their Gauteng facility in City Deep and with newly acquired national distribution contracts, needed more low temperature storage space. In a record time of only 18 months from conception, the store was commissioned and started receiving product. “After considering all our options, we decided on a large new warehouse in the extension of Linbro Industrial Park,” says Anthony van Zyl, national warehouse manager, Imperial Cold Logistics. Fortunately most of floor of the 23 000m2 warehouse had not been completed and could be cast to accommodate the underfloor insulation and heating needed for all the low temperature stores and the rails for the mobile racking. A total of 371km of heating cable was laid beneath the concrete floor! Central ammonia refrigeration The insulated panelling contract was awarded to Isowall and the design and contract for the central ammonia refrigeration plant, was negotiated directly with Multistage Cooling. “In a matter of three weeks we had completed the design, agreed upon a contract price and started with the fabrication of the valve stations,” explains Bob Vuletic, owner of Multistage Cooling. Vuletic and his team gained access to the site on 8 June 2015 and by 27 November 2015, 50% of the plant was operational and able to receive product. When built, the roof structure did not allow for the extra mass of evaporators, but this was overcome by selecting stainless steel coils which are much lower in mass than the conventional galvanised steel coils. Because of the time restraint, Multistage pre-manufactured all the valve stations at its Randburg workshop and then transported to site. Each evaporator, including those in the air lock (dispatch and receiving area), is mounted in an insulated pod with a hydraulically operated flap that closes when the coil is defrosted. Being in a pod, the defrost time is shorter and the possibility of moisture being blown into the room, minimised. 2 3 A total of 371km of heating cable was laid beneath the concrete floor! Valve stations are individually mounted in insulated enclosures with an ammonia leak detector to automatically shut off the supply of ammonia in the event of a leak. The enclosures allow for repairs to the valve station or replacement of a component to be done without any interference with the piping insulation. Not having to be concerned about the pipe insulation will also reduce the time of any repairs or maintenance needed to be done on the valve stations. Piping and vessels are insulated with preformed polyurethane and a ‘Foil-toMylo’ vapour barrier protected by stainless steel cladding done by Intertherm. 4 1 5 1. Close co-operation between client and contractor was needed to complete the contract in a short period, from left: Anthony van Zyl (National Warehouse, general manager), Brink Heinemann (manager, Linbro Park), and Bob Vuletic (Multistage Cooling, owner). 2. Valve station to change ammonia flow between surge drums according to demand. 3. Line-up of seven of the Grasso reciprocating compressors in the plant room. 4. Two of the reciprocating compressors operate on the low-low stage, -40°C. 5. Imperial Cold Logistics has a network of seven cold stores around South Africa. 36 www.coldlinkafrica.co.za COLD LINK AFRICA • May | June 2016