INCORPORATING COLD CHAIN
PROJECT
2 3 4
1 . Due to the structural aspects of the site , the sign at the forecourt doubles up to hide away the extract air ducting
2 . An inside view of one of the display fridges .
3 . All of the pipework had to match the overall colour scheme of the store .
4 . The existing chiller plant area that services the rest of the floors above .
5 . Some of the condensing units are installed at the back of the building .
6 . The chilled water pipes from the plant room had to be altered re-installed because of the site alterations to include an additional staircase .
7 . The back of house storage freezers .
8 . The chiller electrical control box – installed out of reach of any wandering fingers .
5 6
7 8
COLD LINK AFRICA • March / April 2022 www . coldlinkafrica . co . za 25