CIS 348 Week 7 Assignment 5 Mobile App Part 2 ( Gantt and Pert Chart )
Update the Microsoft Project file you created in Assignment 4 : Mobile App Part 1 ( Work Breakdown Structure ) with the following changes :
Set progress in at least ten ( 10 ) of the line items .
Set the properties so that at least one ( 1 ) of the main tasks is behind schedule .
Create a Gantt chart for the project .
Take a screenshot of the Gantt chart which can later be inserted into your written paper .
Create a PERT diagram that identifies the critical path .
Take a screenshot of the PERT chart which can later be inserted into your written paper .
Note : If you need a tutorial on taking a screen shot , visit one of the following locations
Write a two to three ( 2-3 ) page paper in which you :
Compare and contrast the information that one receives from a Gantt chart , versus that of a PERT diagram .
Examine the advantages of using a Gantt chart over a PERT chart and vice versa . Determine when it is appropriate to use one over the other . Justify your response .