CIS 348 MENTOR It's Your Life/cis348mentor.com CIS 348 MENTOR It's Your Life/cis348mentor.com | Page 9

FOR MORE CLASSES VISIT www. cis348mentor. com

CIS 348 Week 7 Assignment 5 Mobile App Part 2( Gantt and Pert Chart)
Update the Microsoft Project file you created in Assignment 4: Mobile App Part 1( Work Breakdown Structure) with the following changes:
Set progress in at least ten( 10) of the line items.
Set the properties so that at least one( 1) of the main tasks is behind schedule.
Create a Gantt chart for the project.
Take a screenshot of the Gantt chart which can later be inserted into your written paper.
Create a PERT diagram that identifies the critical path.
Take a screenshot of the PERT chart which can later be inserted into your written paper.
Note: If you need a tutorial on taking a screen shot, visit one of the following locations
Write a two to three( 2-3) page paper in which you:
Compare and contrast the information that one receives from a Gantt chart, versus that of a PERT diagram.
Examine the advantages of using a Gantt chart over a PERT chart and vice versa. Determine when it is appropriate to use one over the other. Justify your response.