Imagine that you work as the project manager for an IT department . Your organization has recently approved the development of a mobile application . As the project manager , you will manage the development of the project . The project will include user experience ( UX ) design by a consultant , graphic design by a team of two contracted designers , and in-house application development by a team of three ( 3 ) programmers and a database developer .
Deliverable 1 : Summary ( MS Word or open source equivalent ) Write a one to two ( 1-2 ) page summary document in which you :
Summarize the project requirements and other assumptions ( i . e ., budget , human resources , workload , environmental dependencies , etc .).
Define a work breakdown structure and describe the methodology behind constructing one .
Deliverable 2 : WBS ( MS Project or open source equivalent )
Use Microsoft Project or an open source equivalent to create a WBS which addresses the following :
Contain at least five ( 5 ) main tasks , one ( 1 ) for each of the PMBOK ® process areas .
Contain at least thirty ( 30 ) line items distributed in five ( 5 ) or more work packages .
Contain Work Breakdown Structure Code for each task .
Present duration estimates for each task that results in a duration estimate for the project not to exceed the requirements described in the overview .