Self-production
Independent producers
|
Authorisation required for electricity projects located outside of the public domain with an installed capacity of between 100 kW and 9,999 kW. These thresholds may be too small in practice for captive power projects.
A decree sets out the terms and conditions for the sale of surplus electricity. However, the notion of“ auto-production” is not expressly defined. To be further investigated with the administration.
License required for electricity projects located outside of the public domain with an installed capacity above 1 MW.
Concession regime applies to projects located in the public domain, as well as to the transport and distribution of energy( no maximum installed capacity threshold identified). 10
|
Authorisations granted by the provincial governor or by the decentralised territorial entity.
To be further investigated with the administration.
Licenses granted by the provincial governor, upon instruction and after examination and approval by the Electricity Regulatory Authority.
Concessions granted following an invitation to tender, or, exceptionally, through a direct agreement.
|
Law No. 14 / 011 of 17 June 2014 on the electricity sector
Law No. 18 / 031 of 13 December 2018 amending Law No. 14 / 011 of 17 June 2014
Ministerial Decree No. 031 / CAB / MIN-ENRH / 2017 of 21 April 2017, setting out the conditions and the procedure for the certification of service providers in the energy sector
Decree No. 18-052 of 24 December 2018 setting out the procedures for selecting operators, awarding, amending and cancelling concessions, licenses, and authorizations in the electricity sector
Decree No.
082 / CAB / MIN / ENRH / 18 dated 27 December 2018
Law No. 14 / 011 of 17 June 2014 on the electricity sector
Order No. 030 / CAB / MIN-ENRH / 2017 of 21 April 2017
Decree No. 18-052 of 24 December 2018 setting out the conditions and the procedure for the certification of service providers in the energy sector
|