– John McManus , Construction Director
CONSTRUCTION
McManus , Construction Director .
Strategic management According to McManus the key to delivering this particular project on schedule has been to have open communication and collaboration with all stakeholders , especially Eastland .
Probuild holds design management meetings to go over any issues , monthly Project Control Group ( PCG ) meetings , several site-based meetings with consultants and subcontractors , and bi-monthly meetings with members of the Maroondah City Council .
Probuild has committed to supporting the existing Eastland Shopping Centre , which has been continuing normal business operations during construction . By forming complex work
“ A major priority of the project and retail projects generally is to maintain as much flexibility as possible for the client to allow leasing-driven changes . This way , scope changes occur with minimal programme and cost implications , as construction progresses ”
– John McManus , Construction Director
www . probuild . com . au 121