Cashflow and additional hardship

Despite the above clarifications, the guidelines also recognise that there is still likely be significant financial consequences for Contractors from the Covid-19 restrictions, which stands to affect the industry and economy as a whole. To that end, they ask government agencies to consider:

a. Other mechanisms to improve cashflow and remobilisation. Specific suggestions include: forward ordering, payment in advance/prepayment, faster payment cycles, issuing purchase orders for costs incurred, interim payments, or for results-based contracts, basing payment values on previous months; and

b. Whether additional extra-contractual financial relief for individual Contractors is warranted and in the public interest. MBIE says it is developing processes for considering and approving requests for special relief.

9

BuildLaw | Apr 2020

Glen Holm-Hansen

Senior Associate

Nick Gillies

Partner

Relevant links

ABOUT THE AUTHORS

Government Announcement

Contract Guidelines

Government guidelines contact: [email protected]

Hesketh Henry Covid-19 Webpage

Christina Bryant