BuildLaw Issue 29 September 2017 | Page 31

The issue which the
court was asked to decide was a simple one: were there one or three contracts between the parties?

- Conway served both a payment and payless notice on RSC. This notice responded to RSC’s single final account claim in respect of the three sites. Conway did not serve three payment notices and three separate payless notices. Again, this suggested that there was only one contract. It also ran contrary to Conway’s assertion that the documents for each project were kept separate.
- Conway’s previous advisers, in a letter, referred to the overall situation in this case as “a job that was sub- contracted”. That was again consistent with there being a single contract.
- Conway was not an entirely satisfactory witness. He raised matters which were irrelevant. He repeatedly referred to documents which were not provided. Most important of all, he had no positive case about the conversation on which Mr O’Rourke relied so heavily. He seemed unable to recall that conversation at all.
- Conway’s case amounted to no more than the assertion that, because there were three separate sites, and three separate bills of quantity and other valuation documents, there must have been three separate contracts.
- It did not follow that, because there might have been different documentation pertaining to the different sites, there were three separate contracts. That was not the burden of the authorities, neither can that be right as a matter of law. All that matters were whether the parties agreed that there was one contract or three. Mr O’Rourke’s evidence on this point was accepted i.e. that, on 19 December 2012, it was agreed that there would be one single contract.
There was one contract in respect of the three sites and a single dispute about what was due under that contract. The adjudicator was to have the necessary jurisdiction to decide that claim. Since that was the only point which prevented the enforcement of the adjudicator’s decision it meant that RSC was entitled now to the sum sought.
The judgment turned on the facts, the oral evidence and the credibility of the witnesses led by both parties – an expensive price to pay for not reducing the construction contract to writing in the first place. This bears relevance to the South African construction sector as well. The South African Supreme Court of Appeal in Stellenbosch Farmers’ Winery Group Ltd. and Another v. Martell & Cie SA and Others 2003 (1) SA 11 (SCA) set out the technique generally employed by courts in resolving a factual dispute about the terms of oral agreements (whether it be construction contracts or otherwise). This general enquiry typically involved a consideration of the credibility and the court’s perceived veracity of a witness; the witness’ reliability; and the probability or improbability of the witness’ version regarding each dispute. A costly affair indeed. To avoid this unnecessary cost and the uncertainty that ensues, parties should, in accordance with best practice, reduce their construction contracts to writing.