BuildLaw Issue 25 September 2016 | Page 26

The role of causation in concurrent delay

By Mark Lloyd-Williams, Ann Levin, James Doe and David Nitek

On 29 July 2016, the Commercial Court issued its decision in
the case of Saga Cruises BDG Limited and Anor v Fincantieri Spa [2016]
EWHC 1875 (Comm).

This case confirms that in some circumstances, concurrent delay (i.e. a period of project overrun which is caused by two or more events – one of which is the employer's responsibility and the other the contractor's responsibility) will not entitle the contractor to an extension of time. In other words, it does not follow automatically that concurrent delay means the contractor is entitled to an extension of time - the issue of causation must always be properly considered.

The basic facts in the Saga Cruises case relevant to the issue of delay are as follows:

• The claimant owners ("Owners") of a cruise ship contracted with the defendant shipyard ("Yard") for engineering and fit out works with the aim of transforming the ship into the Owners' flagship.

• The engineering and fit-out works were scheduled to start on 9 November 2011 and be completed by 17 February 2012. However, the works were considerably delayed and the scheduled completion date was postponed to 2 March 2012 by agreement.

• During the period of the works, there were a number of delays to the scheduled completion date some of which were the responsibility of the Yard, and others the responsibility of the Owners. Ultimately, this meant that the ship was not delivered to the Owners until 16 March 2012. The causes of the delay included the following:

- The Yard was responsible for creating new cabins by converting the available space on one of the decks, and for installing a proprietary decking system. The Court held that this work was not completed before 16 March 2012 and 12 March 2012 respectively.

- The Owners were responsible for the lifeboats. The Owners discovered major issues with the weight of the lifeboats which resulted in delays between 3 March 2012 and 14 March 2012.

- The Owners were responsible for requesting that the Yard install additional insulation which led to a delay between 2 March 2012 and 10 March 2012.

One of the issues in the case was whether any, or all, of the periods of delay for which the Yard was responsible were also the fault of the Owners and therefore concurrently caused.

The Owners submitted that, if completion of the works was already delayed by risks for which the Yard was responsible, then delays to completion that were the responsibility of the Owners (including, for example, the work associated with the lifeboats and additional structural fire insulation), were not to be treated as recoverable delay and did not entitle the Yard to an extension of time.