Breaking New Ground—Stories from Defence Construction Breaking_new_ground | Page 67

Has there ever been anyone who worked in the construction industry in Canada who didn’t dream of a warm, dry, windless and well-lit place to work in the winter? Well, at CFB Valcartier such an environment was created in the winter of 1971–72! … The first package off the drawing board in the major construction management project was the foundations and superstructures for four new “Other Ranks Quarters.” Despite everyone’s best efforts, the superstructure tender was called late in the summer… Nothing much could be done to advance the schedule and nothing at all could be done to delay the onset of winter. A solution came from Phil Coulter, an employee of the consulting engineering firm of A.D. Gagnon and Associates… to purchase and install two air-supported structures (balloons as everyone called them) as soon as the foundations of the first two quarters were completed and backfilled. The superstructures could then be constructed in these dry, heated air-supported structures. When the first two superstructures were completed, the balloons would be dismantled and transferred to the last two quarters buildings. (The balloons) were the largest ever used on a building project, and it was the first time they were used in severe Canadian winter conditions… The air-supported structures were held up via pressurization… (they) were really just very large floorless tents. A wide flap at the perimeter was turned inward and weighed down with sand. The fabric was like a coated white canvas and allowed sufficient light to pass through that artificial light was required only in hours of darkness… The spaces created were very conducive to work. They were about 20 metres high, 40 metres across and 70 metres long. On entering the structures, one had a strong impression of immense space… BREAKING NEW GROUND DEFENCE CONSTRUCTION CANADA Within six weeks of work, the superstructures were about 80 percent complete, a rate of progress that Atchison noted could not have been maintained even in summer conditions—but the position of the backup power generators, which had been placed outside the balloons because of concerns about fumes, was about to become a problem. On the night of the first Friday in February, a major winter storm hit the Quebec City area. Several hours into the storm, power failed at the Base. The generators cranked, but they never caught—there was too much snow everywhere, including under the cowlings of the generators. As pressure was lost, the fabric on both balloons became loose and began to flap in the wind The superstructures had thousands of sharp masonry points, projecting reinforcing rods and metal door frames. The fabric literally ripped itself to shreds. Both air-supported structures were totally destroyed. Completion of the quarters buildings was delayed until spring. Two new structures were ordered for the final two quarters buildings, and the generators were this time installed inside. Before work began, however, the fabric on one structure failed during high winds and was again ripped to shreds. The fourth balloon was more successful—although it, too, suffered a fabric failure. They (structures) were a success in that they created a reasonable place to work in winter. Nevertheless, we have to consider cost. All of the tradesmen who were employed on the project could have been paid to stay at home for the whole winter and it would have cost less. The value of the construction that would have been executed under the balloons, even had the collapses not occurred, was less than the cost of the structures, their installation and maintenance… the technique has not been used since for winter construction in Canada. 57