Beargrass Creek Trail Conceptual Shared Use Path & Ecological Restora Project Limits and Focus Areas | Page 52
Preliminary Cost of Ecological Restoration Opportunities
•
•
Preliminary planning estimate for ecological
restoration is $4.5 – $6.0 Million
Includes:
–
–
–
–
–
•
Measures A1 – H1
Design
Permitting
Construction
Monitoring (as required)
Impound
Lot
Does NOT Include:
– Remediation of River Metals, Impound lot,
Reynolds property, or the Oakleaf property
– Invasive species management along both
banks of 3 mile project length (measure B1
may be applied at other locations)
– Bank stabilization along both banks of 3 mile
project length (measure D1/G2 may be applied
at other locations)
– Potential stream restoration of Area I
Oakleaf
Property
River
Metals
Area I – Potential stream
restoration
Public Meeting #3 -- December 6, 2016