BDC Magazine - Online version December 2015 Issue - 216 | Page 121

Transport News.qxp_feature 2 21/10/2015 12:22 Page 119 Gatwick accuses Heathrow of facing £6bn third runway funding shortfall over surfacing work H eathrow is facing a “funding black “As we approach a decision on expansion, Heathrow hole”, with the airport and the govern- owes taxpayers, passengers, airlines and government an ment unwilling to provide the £6bn explanation of how they plan to meet it, as this cost increase required for surface works on its pro- alone is almost the entire cost of the Gatwick scheme.” posed third runway, Gatwick Airport’s chief executive has said. Heathrow has hit back at Mr Wingate’s claims, with a spokesman for the airport saying the “Minister has simply Gatwick CEO Stewart Wingate said the planned surface restated what is already government policy.” According to works, which include the tunnelling of the M25 and a new Heathrow, it would only require £1bn for the road and rail rail line to connect Heathrow with Victoria, would cost upgrades and this could still be covered by the government. Heathrow £6bn and challenged the airport to explain how it would fund the work. Government policy states that “the general position for existing airports is that developers should pay the costs of Mr Wingate claimed that Heathrow and the government upgrading or enhancing road, rail or other transport net- have both shown they were unwilling to foot the bill. His works”. However, where the scheme has a “wider range of comments came after transport minister Robert Goodwill beneficiaries”, the government “will consider the need for said in parliament yesterday that the government would not additional public funding on a case-by-case basis”. cover the costs for rail and road improvements to go alongside the third runway expansion. Mr Goodwill said: “In terms of surface access proposals, Heathrow believes some of its surface work projects would provide a wider range of benefits and as a result could be eligible for government support. the government has been clear that it expects the scheme pro- In July, the Airports Commission recommended moter to meet the costs of any surface access proposals that Heathrow ahead of Gatwick as the preferred location for air- are required as a direct result of airport expansion and from port expansion in London. which they will directly benefit.” The decision was met with opposition from some politicians Mr Wingate said this highlighted the government’s as well as Gatwick Airport, which has questioned Sir Howard resistance to financing the project. “There is now a £6bn Davies’ recommendation on the grounds of air pollution and black hole at the heart of Heathrow’s plan,” he said. “complexities in construction” not being fully considered. “Heathrow has said it won’t meet the bill and now the government has done the same. Heathrow began the tendering process for the preparatory work on the runway this week.