Australian Water Management Review Vol 1 2010 | Page 36
Black & Veatch
In early 2006, Black & Veatch and their
consultancy partners were appointed by
the Queensland Government to carry
out preliminary design for the overall
Western Corridor Recycled Water
Project (WCRWP), which comprised
three Advanced Water Treatment (AWT)
Plants, as well as the distribution network
and major pumping stations. Review of
the existing business case confirmed
the viability of the project; but crucially
the team came up with an optimised
treatment strategy, which resulted in
significant project savings.
In this design, treated water either could
be used locally in areas around each of
the AWT Plants or at potential sites along
the length of each transfer pipeline, or it
could be readily combined at Bundamba
for transfer along the Western Corridor.
This transfer offered a range of uses,
including power station cooling, irrigation
or industrial applications, or to storage at
Lake Wivenhoe for indirect potable reuse.
Due to the importance of the WCRWP to
the people of Queensland and the desire
to ensure that the project was started
as early as possible, the joint venture of
Black & Veatch/Thiess Construction and
Western Corridor Recycled Water Pty
Ltd, or the Bundamba Alliance, was made
responsible for designing and constructing
the 66ML/d Bundamba AWT Plant in June
2006. The alliance worked in partnership
with the Queensland Government’s
Department of Infrastructure and Planning
to deliver the project.
The contract to design and construct
Bundamba Stage 1A was awarded with a
completion date of 3rd Quarter 2007. In
order to meet this date, the project team
had to focus on how to build the plant in
a very short period. The basic treatment
process and major operating parameters
had already been established during
Water Management Review 2010
the preliminary design stage. However,
major equipment had to be selected not
only on lowest capital and operating cost
but also on ease of construction and
effect on civil works.
With these criteria in mind, the project
team selected equipment that would
minimise excavation and shorten
construction time as well as maximising
off site erection and testing. This resulted
in the selection of encased skid-mounted
pre-treatment and RO membranes and
in-pipe UV equipment. Major tankage was
designed to be entirely above ground to
maximise pre-casting.
A key challenge for the Bundamba
AWTP was how to treat a blended
flow from four wastewater treatment
plants, each with a different treatment
process and configurations and
different effluent qualities.
The main treatment steps of ultrafiltration membranes, reverse osmosis
(RO) membranes followed by advanced
oxidation using UV irradiation and
hydrogen peroxide together represented
the gold standard for water reclamation.
This was the first full-scale facility
designed to meet such stringent
nitrogen, disinfection and emerging
contaminant quality parameters and also
the first large-scale application of 18”
diameter RO membranes. Large diameter
membranes were chosen for their
lower capital cost; fewer membranes
are required for the same throughput
resulting in less maintenance and a lower
plant footprint.
Advanced oxidation was added as
a treatment step to ensure that the
purified recycled water met the required
guidelines for water recycled to a drinking
water source. Purified recycled water will
be added to Wivenhoe Dam should levels
in the dam fall below a certain threshold.
As well as having a team based on the
project site, Black & Veatch through
its concept of the Integrated Global
Workforce was able to carry out design
work in China, India, Singapore, UK and
US, bringing the benefit of global solutions
to a local problem.
Progress was faster than many thought
possible. Stage 1A was officially opened
in early in September 2007 after
ground breaking was carried out only in
November 2006. Working closely with
partner Thiess, Black & Veatch led the
start up effort and detailed testing and
commissioning plans were developed.
Quality was maintained and safe working
procedures were strictly adhered to with
over 1.7 million hours worked without
Lost Time Injury.
In 2008 and 2009, the Bundamba
AWTP received numerous national and
international accolades from the global
engineering community. These included
Water Project of the Year at the 2008
Global Water Awards, International
Project of the Year by the Construction
Management Association of America,
Global Honour award for Design
Category at the 2008 International Water
Association (IWA) Project Innovation
Awards, and winner of the Environmental
Engineering Award at the 2008 Engineer’s
Australian Engineering Excellence Awards.
In November 2009 the plant was named
as one of the top ten engineering wonders
in Queensland.
Contact Black & Veatch at:
Brisbane: (07) 3010 9445
Melbourne: (03) 8673 4200
Perth: (08) 9436 8900
Sydney: (02) 9019 0600
[email protected]
www.bv.com