communicated to other non-technical members of the team . Virtual walk-throughs of the model were done with the client on a periodic basis to gain a better understand of the building . Walking through the building in this manner also allowed the client to make recommendations to the design team around facilities management issues etc .
The main contractor , Stefanutti Stocks , also embraced the virtual design space and models were shared with the site team to understand
the building better . Virtual walk-throughs were conducted with the site teams in order to address various queries on the project . The adoption of BIM on the Park Square development has allowed the design team to deliver a technically challenging building on a tight construction schedule in an efficient and coordinated manner .
Clash detection was a big driver for the design team when deciding to adopt BIM on this project . Clashing of services with each other or
608 Park Square