GROUND FLOOR PLAN
FIRST FLOOR PLAN comprises a skeleton crew , the nature of work and AAA finishes required that the quality and composition of this team mirrored that of a day shift ”, said Johan Bezuidenhout , NMC Contracts Manager .
The location of the services proved to be challenging for contractor and designers alike , with 30 year old built drawings merely giving an indication of what could be expected .
These presented several ‘ surprises ’ on a daily basis , further impacting on the tight project programme . The process was carefully managed in collaboration with contractor , designer , consultant , engineer , sub-contractor and supply chain and with good team synergy identifying swift solutions and effective management of programme , cost and quality was achieved .
Nelson Mandela Square 521