In addition to the building
design, Peerutin was
commissioned to design
and procure the complete
interior package
GENERAL DESCRIPTION OF SERVICES
Electrical
Roeland Park has a medium voltage 11kV
electricity supply from the City of Cape
Town Electricity Department. The 24/7/365
requirements for the transmission facilities
necessitated that all power for Roeland Park is
ETV Head Office
backed up by diesel fuelled standby generators
which automatically switch in when there is a
power failure.
The generator sets have a 14,000 litre diesel
tank to make sure that there is always sufficient
reserve supply – this should last between 2 and
4 days in the case of a blackout.