Architect and Builder Magazine South Africa September/October 2014 | Page 28

Amsteele Systems Aid Fast Track Programme on 102 Rivonia Road A fter a successful open tender process, Amsteele Systems were appointed, in late 2012, by Murray and Roberts’s Construction (M&R) for the design, supply and installation of the post-tensioning works on the prestigious 102 Rivonia Road office block in Sandton, Johannesburg. The building was developed by the Eris Property Group for main tenant, Ernst & Young. Initially, only Basements B7 to B1 were post-tensioned with a total area of 47,436m², with partial post tensioning to the tower block levels, located mainly along slab edges for deflection control, due to the glass façades of the building. The main contract was won by M&R based on a fast track construction programme. Site occupation by M&R was in June 2012, with the Ernst & Young tower having to be completed by End October 2013 and the entire contract handed over at the end of January 2014. 28 After the award of the contract, it was proposed by Amsteele to fully posttension not only the basement slabs, but all levels of the tower blocks, to speed up the construction process in order to give the finishing trades quicker access to the completed floors. After due consideration of all the benefits by the professional team, as well as the main contractor, the proposal was accepted, as it was evident that this was the only way that the extremely ambitious contract programme could be met. This resulted in an additional 40,405m² of post-tensioned slabs, bringing the total area of PT slabs to just under 90,000m². The most challenging aspect of the contracts was the fast track contract programme. The site was operational 24 hours a day, seven days a week, for much of the contract period; added to this were the numerous work faces being worked on simultaneously, extremely limited laydown areas on site, the logistics of getting the materials to site and straight onto the deck being worked on. The contract programme also only allowed a two day period to fix both reinforcing and post-tensioning for each pour, with each having an average area of 600m². Due to the complex architectural design, each floor layout was different to the preceding floor, which made the design and detailing of the slabs extremely challenging. All challenges were overcome and the contract was completed on schedule, mainly due to excellent team work between the professional team, main contractor, Amsteele and its reinforcing suppliers and also Amsteele’s in-house design engineers. Advertorial