Architect and Builder Magazine South Africa November/December 2014 | Page 28

The majority of staff and visitors will take the bank of shuttle lifts located on the Grayston edge of the site up to the atrium level on top of the parking structure Landscaping A combination of internal planting to pause areas, atrium trees and roof terrace planting at the atrium level ensure that although this is a building in the heart of the business heart of Africa, nature is never far away. Trees in the atrium on the floor and the feature balcony overlooking the atrium provide human scale and soften the acoustics of the tall space. Sustainability As part of the best-practice good business journey, the 90 Grayston building is a sustainable one which achieves a minimum of a 4-star GBCSA green building rating. A combination of sensible passive design principles and selected active technologies were used to minimise the impact of the building and its ongoing use on the environment. These include the use of a highefficiency ammonia chiller HVAC system and the harvesting of rainwater to flush toilets. 28 Construction & Engineering The considerable challenge for the main contractor, WBHO, was to construct a 21 storey building on a relatively small site of ±45m by 83m with various restrictions due to the three neighbouring buildings and a busy Grayston Drive in central Sandton on the 4th boundary. Due to the restricted site access and the variable rock on site the tight program deadlines was always going to be challenging, even though the main contractor managed to erect 3 tower cranes on the small site. The lateral support for the five level deep basement was constructed using 600mm diameter piles with 200mm gunite arches that extended 17m in depth at the South face into the typical Sandton soil profile. This soil profile was a combination of soft sand and soft weathered granite rock with a hard Diabase intrusion requiring blasting lower down slowing down the program. Due to the variable nature of the founding conditions a combination of piles and pad footings were chosen for the foundations and these could only be finally determined as the excavation depth was near completion allowing piling contractor, Franki Africa, to probe the rock level. The main structure has five basements and six levels of parking above ground with ten levels of office space above that on a grid of 8.4m by 7.6m. The parking slabs were constructed with 230mm post-tensioned slabs and the office slabs were 270mm postTensioned. The main stability elements were the central core and two smaller stair shafts at either end providing lateral stability to the long building. On the north side of the building the floor plates from office level 3 upwards to level 9 project out gradually in increments of 1.48m into the Atrium space with raking columns 90 Grayston