Architect and Builder Magazine South Africa July/August 2014 | Page 11

PROJECTVIEW WATERSTONE BUSINESS PARK, CAPRICORN PARK efficient buildings in Sandton. It is also set to become a landmark on the Sandton skyline. Green building plays a key role in providing spaces in which businesses can thrive. For Discovery, it will create a stimulating working environment and reduce building utility costs with sustainable alternatives.” “Offices should integrate flawlessly into our clients’ businesses and provide people with a positive, healthy and energising environment,” says Pienaar. “This means creating user-friendly offices and solutions through innovation and creative design that push the boundaries. Working with Discovery has created the foundation for an operationally efficient, sustainable building that promotes increased staff retention and productivity, improved asset performance, reduced operational costs and much more.” Zenprop Property Holdings CEO, James Tannenberger says: “This iconic building will be the largest single office development to take place in Africa. Accordingly, we have assembled a highly skilled project team in order to meet the inherent demands of a complex and multi-faceted delivery process, whilst integrating Discovery’s specific requirements into the broader planning and design processes. This will ensure that this prestigious development meets the unique business needs of Discovery, now and into the future.’’ The new head office will provide many unique advantages for Discovery. It will serve as the company’s hub for its growing international business. It will bring all of Discovery’s more than 5,000 Sandtonbased employees under one roof, instead of the current situation, where employees work across four buildings. Earthworks for the development are well underway. Developer: Growthpoint Properties; Zenprop Property Holdings Architect: Boogertman & Partners Main Contractor: WBHO and Tiber in a JV Estimated Completion Date: Early 2018 FWJK Quantity Surveyors has followed up on the success of it’s R200 million Touchstone House development currently under construction in Bree Street, Cape Town, with the launch of a new mini factory development at Capricorn Park to be known as Waterstone Business Park. The 5,600m² industrial development will comprise 13 mini factories varying in size from 289m² to 607m² in a location that is proving popular for industrialists wanting to relocate to avoid traffic congestion whilst having the benefit of a large labour pool nearby. Developer: FWJK Developments Architect: Tim Hughes Architect Quantity Surveyor: FWJK Quantity Surveyors Structural Engineer: Bergstan Consulting Engineers Electrical Engineer: Converge Consulting NEW STUDENT CENTRE, UNISA REGIONAL CAMPUS, POLOKWANE, LIMPOPO The construction of a new seminar room for the students and offices for their use is underway. Client: UNISA Architects: Prism Architects Quantity Surveyors: KC Maiwashe and Associates Consulting Structural & Civil Engineers: Ny eleti Consulting Main Contractor: Matakanye Construction Value: R54 million Commencement: December 2013 Completion: ± March 2015 (Leads to Business) Project Watch 11