Architect and Builder January/February 2016 | Page 37

Architectural or Engineering Challenges As with any project involving heritage buildings, one should expect the unexpected. Initial surveys of the buildings (pre-demolition) did not seem to indicate major issues, but once basement level of the adjacent building was reached, it became clear that the engineers were going to be in for an interesting time. The basement foundations were stone packed and in order to install the lateral support piles, about 1m of space in the basement had to be forfeited. The next surprise came when the survey of the excavation was received. The same building exceeded the erf boundary in an ever increasing manner, ending up a further 700mm into our property. This caused a major rethink of the escape routes and staircases in the area. While the demolition and excavation was in process, final plan approval was in progress. FWJK Developments had already received provisional approval to commence with construction to ground level, when the Local Authority notified us of a land dedication that was made to the Council in the late ‘50’s. A 36m2 portion of land included in the design was affected by this dedication. This was not picked up during the due diligence period as the dedication was never registered against the property title deeds, but it was subsequently found to be legal and in effect. Plans then had to be amended to exclude this portion of the site in order to achieve plan approval and FWJK was forced to apply to purchase the land from Council and, on conclusion of the public process, we had to resubmit the plans with the dedicated section included. concrete structure with downstand beams to stiffen the edges of the slab and also to function as the lintels for the linear window elements. All walls are conventional brick infill construction. The glazing of the building is partially conventional glass and part curtain wall. We made extensive use of Marmoran products on the external façade, partially because of the durability of the product, but also because it has the inherent ability to smooth out minor imperfections that tend to become very noticeable once the scaffolding is removed from a building. A specialist plasterer did some excellent remedial work on the historic façade and the majority of the damaged timber windows were either refurbished or in the instances where the fire damage was too substantial, were replaced with custom made windows. Description of Material Used The construction methods are generally conventional. Use was made of a post tensioned Touchstone House 35