Architect and Builder December 2019 | Page 84

Omnia Nitrophosphate Plant SAISC STEEL AWARDS INDUSTRIAL CATEGORY Omnia is a diversified chemicals group that supplies chemicals and specialised services and solutions for the agriculture, mining, and chemical application industries. Differentiation is ensured through using innovation combined with intellectual capital, whereby Omnia adds value for customers at every stage of the supply and service chain. With its vision of leaving a ‘better world’, the group’s solutions promote the responsible use of chemicals for health, safety and a lower environmental impact, with an increasing shift towards cleaner technologies. A new quality control system was implemented internally at SE Steel Fabrication. All fabrication had to be done with a high level of accuracy. This was essential to prevent steelwork arriving on site and possibly requiring additional remedial work before installation, so a best- fit approach was adopted. Any remedial work may have placed the integrity of the anti-corrosive paintwork at risk in an already corrosive environment. Limited space was available for steelwork, so a laydown area was created approximately one kilometer from the actual site. This being the situation, the steelwork contractor placed a 20 ton crane and a horse and trailer permanently on site while the project was running to ensure the correct sections and steelwork were being fed to the site. Ultimately to prevent delays, there was a need to plan for tomorrow's erection today, to avoid unnecessary standing time. Executing advanced planning on site allowed the team to remain on program. Full penetration welded, purpose made columns were used on the Main Plant. 3CR12 was selected for the purlins and girts. The paint was a complex sand blasted, epoxy corrosion specification to ensure longevity. Numerous safety challenges were faced during the tight deadline to complete erection on this 1,200 tonne project. A dedicated safety officer was permanently placed on site to ensure all safety compliance was met on the contractor's part. This proved effective with a less than 1% accident rate during the entire span of the project, including all trades. This number needs to be taken into consideration knowing that there were numerous trades working on multiple levels of the structure at the same time, the whole time. Tight spaces meant that cranes and cherry pickers had to be strategically placed in order to reach all necessary corners and the required heights, often while other trades were working on the various levels of the structure. This also meant that work was halted while wind conditions worsened during the erection process. In total, there were two 44m articulate boom cherry pickers, a 220-tonne, 160-tonne and a 50-tonne crane on site the full duration of the project excluding the laydown area machinery as listed above). Planning, erection and the project program were cast in stone with a strict deadline, regardless of the weather. There was no time to be wasted. All had to be done in one year from design to being fully operational. Installation crews and machinery from Europe were due to install their scope of work to ensure that this strict program was implemented, so adhering to the deadline was imperative. Client: Omnia Fertilizer Engineering & Project Manager: Omnia Group – Group Technical Projects Project Manager: SE Steel Fabrication Main Contractor: Omnia Fertilizer Steel Fabrication and Erection: SE Steel Fabrication Cladding supplier and contractor: M.R.G. Paintwork Contractors: Dram Trading, Rand Sandblasting Projects Steel Detailer: SSD Detailing & Engineering Services 84 Steel Awards