Project Timeline
The first designs for the building as we see it today
started in May 2014. Over the next year and a half
the building design was technically resolved and
the first council submission for planning consent
was submitted in December 2015. Planning
approval was obtained in September 2016.
Demolition of the existing Endee Building then
started in September 2016 with the construc-
26
tion of three phases starting in April 2017. The
occupation of the final phase was achieved in
December 2019.