All project components were designed by Smartroof and manufactured in its state-of-the-art production facility in Derbyshire .
The offsite manufacturing process offered significant advantages including enhanced precision and quality control , improved health and safety and minimisation of material waste . By prefabricating as much as possible , Smartroof significantly reduced on-site construction time and improved overall safety during installation .
The efficient use of the limited site space was essential , with close monitoring of crane placement and layout by all teams to make installation smoother .
“ As Smartroof ’ s Head of Contracts , I ’ m proud to say this was one of our most ambitious housing projects to date . The complexity of this site demanded proactive communication between engineers , designers and site managers .
With the limited availability of cranes , our innovative design approach provided an effective solution , ensuring the project ’ s schedule without compromising Smartroof quality .
This collaboration demonstrated the expertise and adaptability of team Smartroof , delivering exceptional results under challenging circumstances .” Said Smartroof Head of Contracts , Jamie Bremner .
The completed project exemplifies Smartroof ’ s capabilities in delivering complex challenges through innovation , collaboration , and expertise .
By providing a bespoke solution that addressed multiple architectural and logistical challenges , Smartroof has once again demonstrated its position as a leader in offsite manufactured roofing systems .
To find out more contact info @ smartroof . co . uk