“ With consumers , businesses and the public sector becoming increasingly reliant on the

digital economy , the demand for data centres continues to grow .
BRUCESHAW
This will successfully reduce the environmental impact of the facility , reduce the carbon footprint , and help contribute to the government goal of a zero-carbon economy by 2030 .
The main power source to the data centre will be supplied directly from National Grid via Ark ’ s new 150MVA substation which will be energized in summer 2021 . The data centre will then be provided with 100 percent renewable energy .
In the event of a mains power failure , gas generators will provide backup power , a cleaner alternative to diesel . The Union Park facility will be the first data centre of its size in the country to no longer depend on diesel backup generators , producing a dramatic reduction in emissions .
The Principal Team on the initiative are : Client : Ark Data Centres Project Manager : Bruceshaw Cost Manager : Bruceshaw Lead Designer : HDR | Hurley Palmer Flatt Architect : NWA Planning Consultant : Savills Landscape Architect : Barry Chinn Associates