DRILLING AT SANANKORO TO EXPAND GROWTH STRATEGY
PROJECTS AND EXPLORATION •
Image by Natanaelginting on Magnific. com
DRILLING AT SANANKORO TO EXPAND GROWTH STRATEGY
Location: Mali Phase: Exploration Resource: Gold
Cora Gold Limited’ s Sanankoro Gold Project has moved to a construction stage and first gold production, the company announced in June 2026.
Following the successful financing reported in the first quarter of 2026, Sanankoro was declared fully funded for production. The company is now focused on unlocking the broader long-term potential of the project through an extensive resource growth and exploration programme, designed to expand the current JORC compliant mineral resource estimate( MRE) of 1 044koz at 1.04g / t Au, extend reserve mine life beyond the current 10.2 years outlined in the 2025 definitive feasibility study( DFS) and support future production growth.
The 2026 drill programme will target both extensions to existing deposits and several highly prospective near-mine greenfield targets, offering the potential for rapid conversion into future mine plan feed.
Bert Monro, CEO of Cora, commented:“ Our 2025 DFS demonstrated that Sanankoro is a robust, high-margin gold project with a 10- year mine life and compelling economics. As we move towards construction and production, the objective of this drill campaign is to expand beyond the initial mine plan to unlock the much larger long-term opportunity across the wider project area we believe is there to be drilled out.
“ With full construction funding now secured, Cora is in the positive position of being able to advance mine development while simultaneously investing in resource growth and discoveries. We believe the current resource base is just the starting point and, as evidenced in previous drill campaigns, Sanankoro will increase in size significantly with more drilling in the coming years, with this being the first phase of that plan.
“ This programme is designed not only to extend mine life, but also to create the foundation for a larger-scale operation over time through additional resources and higher production potential with continued exploration success.”
The 2026 MRE growth drilling programme is expected to comprise more than 12 000m of drilling, predominantly RC drilling. Initial drilling will focus on four of the five existing deposits at Sanankoro, with Zone B receiving the largest allocation of metres due to its significant growth potential, with the MRE model being predominantly constrained by a lack of drill coverage along strike and at depth.
The company believes there is strong potential to increase both the scale and continuity of mineralisation at Zone B through additional drilling and while not the primary objective of the programme, sections of the drilling are also expected to convert additional mineral resources into the Indicated category, supporting future ore reserve growth.
Zone B comprises three separate deposits: Zone B South, Zone B Central and Zone B North; all hosted along the same mineralised structural corridor associated with the Sanankoro Structure, located within the hanging wall of the Sanankoro Main Shear Zone( SMSZ). Collectively, the three deposits extend over approximately 3.7km of strike length.
No drilling is currently planned at Zone B North as part of this programme( current JORC compliant MRE of 2.6 Mt at 0.93 g / t Au for 78koz), with the initial focus directed towards expanding and improving the continuity of mineralisation at Zone B South and Central, where the company believes there is strong potential for near-term resource growth.
A representative drill section between Zone B South and Zone B Central highlights the scale and continuity potential of the mineralised system. The mineralised zone is approximately 80m wide and remains open down-dip, with current drilling only partially constraining the deeper extent of the system. The section also demonstrates the significant oxide-hosted mineralisation located between the existing reserve pits, further supporting the potential for future resource growth and mine plan optimisation.
Selin Selin is the largest individual mineral resource at Sanankoro, currently hosting a JORC compliant MRE of 430koz( 12Mt at 1.1g / t Au), and remains a key focus for future resource growth. Importantly, Selin already contains significant mineralisation extending below the base of the current MRE pit shells generated using a gold price assumption of USD2 400 / oz under the JORC Reasonable Prospects for Eventual Economic Extraction( RPEEE) criteria. The company believes there remains substantial scope to expand mineral resources both along strike and at depth.
The planned drilling programme at Selin will primarily focus on the southern portion of the deposit, where historical drilling remains relatively shallow and widely spaced, limiting the current interpretation of mineralisation continuity and overall scale potential.
In addition, drilling will target a separate western mineralised zone located outside the current reserve pits, but within the broader USD2 400 / oz MRE RPEEE pit shell. Continued definition of this parallel zone has the potential to deliver additional near-pit mineral resources and further enhance the long-term development potential of the deposit.
Reference:
1. https:// irtools. co. uk / 23 / story / pdf / d1a6c76f-b69b-4471-af35- a2c5852fdab0
Source: supplied by Cora Gold Limited