African Mining September 2019 | Page 9

PROJECTS AND EXPLORATION  BUCKREEF DRILLING PHASE 2 BOOST FOR DRILLING • Location: Tanzania • Phase: Exploration • Resource: Gold • Location: Botswana • Phase: Exploration • Resource: Copper T anzanian Gold Corporation has announced results from three holes that bring an end to phase one of the in-pit drilling programme at their Buckreef gold project in Tanzania. Tanzanian Gold Corporation announced a three-phase drilling programme in January this year. The primary objective of phase one was to upgrade inferred resources within the open pit and to add additional ounces. According to James Sinclair, executive chairman at Tanzanian Gold Corporation, the company has drilled a total of about 4700m during the phase one pit infill drilling programme. "Our open pit and the substantive mineralised zones we are confirming both in, and below the pit continue to impress. I believe we are seeing our thesis of wider, deeper, richer being confirmed as we progress our drilling programme from phase 1 into phase 2. Intersecting 89.6m of continuous gold mineralisation outside and below the pit is spectacular and bodes well for our future," says Sinclair.  L ondon Stock Exchange AIM listed Metal Tiger has announced a further USD1.1-million equity investment into Botswana-focused explorer Kalahari Metals. Metal Tiger currently owns 50% of the issued share capital. The additional investment will enable Kalahari Metals to complete its planned first round drilling at the Ngami copper project and the Okavango copper project, both in Botswana. The cutting of access tracks for the 2100m diamond drill programme started, on schedule, last month, and drill rigs will be mobilised this week. According to Michael McNeilly, CEO of Metal Tiger, the additional funding will allow Kalahari Metals to plan further work programmes over its license holdings. “The Kalahari Copper Belt is highly prospective, and we are confident that continued exploration work in the region will potentially result in new, exciting copper discoveries,” says McNeilly.  SYAMA ON SCHEDULE • Location: Mali • Phase: Development • Resource: Gold Following the commencement of sublevel caving in December 2018, the key elements of the ramp up of the Syama underground mine consist of infrastructure, development, and the automation implementation programme. According to John Welborn, managing director and CEO at Resolute, the company will continue focusing on the successful production ramp up to nameplate capacity and the completion of full automation of all aspects of the sublevel cave in 2019. The June 2019 quarter saw substantial progress in development rates, drill and blast performance and sublevel cave drawpoint availability. This has resulted in a significant increase in the total blasted ore tonnage. The haulage improvement has been achieved by the successful development of additional production slots which has allowed the number of active stoping areas (drawpoints) to be increased from six to twelve. As current stoping activity is occurring on the first production levels of the cave, a significant quantity of the ore blasted in the stopes is retained in-situ in order to create an ore blanket against future hanging wall dilution. These ore tonnes will be recovered from the lower levels of the mine. Consequently, the blasted ore tonnage for the June 2019 quarter exceeded mined (hauled) tonnage by more than 250 000 tonnes. According to Welborn, the underground pumping systems are now fully installed and operational. In addition to the underground pumping facility, a surface water management programme is in place, which allows the mine to intercept and remove a large volume of rainfall that would otherwise enter the mine during heavy rain events. The permanent primary ventilation system was installed and commissioned during the March 2019 quarter and has resulted in reduced re-entry times following blasts. www. africanmining.co.za African Mining Publication R esolute Mining’s Syama Underground Mine in Mali has achieved commercial rates of ore production having mined and hauled in excess of 80% of nameplate mine capacity. Syama will be the world’s first fully automated underground gold mine and at full capacity will produce about 46 000 tonnes of ore per week, or 2.4 million tonnes per year, using a fully integrated automated mine fleet. All key aspects of the mine are now operational with daily ore haulage rates regularly above 5 000 tonnes per day. Work at Resolute Mining’s Syama underground mine remains on track. Welborn states that the commissioning of the Syama Underground Automation System is now well underway with operators in the newly completed surface control room able to control underground production units over shift-change, blasting and re-entry periods, when there are no personnel in the underground mine. This represents the initial delivery of one of the main benefits of automation, the ability to maintain production over periods when operations would normally cease in a typical manual mine. The fibre optic backbone and mine-wide wireless network is now complete from the portal down to the 1055 haulage level and is connected to the surface control room. This network enables the operation of the automated haulage loop, automated rehandle level, mine digitisation and production automation, all of which allow operators to monitor and control mine production in real time. A major technical characteristic of the world’s first fully automated haulage loop is the ability for Syama’s haul trucks to rapidly transition from laser-based underground navigation to surface-based differential global positioning system (GPS) navigation. Recent trials at Syama have demonstrated Resolute’s haul trucks are able to acquire the feed from the two surface GPS base stations and seamlessly lock onto satellite guidance to complete the transition to GPS navigation without any delay or speed reductions. The next phase of automation work will see the commissioning of the 1055 haulage level with automated rehandle loaders and haulage trucks working together to load from an ore pass and truck directly to the surface ROM pad. With the fans, pump stations, control room and communications network complete, the automation project is being progressively handed over to the operations team which is now at normal operational manning levels.  African Mining African Mining  September 2019  7