The first thing that struck me about Optimum Colliery was not the scale of the operation, but the silence.

As our convoy moved through the sprawling Mpumalanga coal complex outside Middelburg, there were workers on site and pockets of activity, yet large sections of the mine felt subdued. Weathered buildings, rusted steel structures and broken windows still stood as reminders of a troubled recent history. In places, the infrastructure appeared suspended somewhere between abandonment and restoration.

Then the scene changed. At the rail siding, black coal dust covered the ground and clung to our boots. Conveyors stretched across the yard, stockpiles were neatly sectioned and loaders moved methodically between the heaps. Later, at the dragline operation several kilometres away, wind swept across fresh spoil piles while a giant machine worked steadily through a new cut. The contrast was striking: parts of Optimum still carry the scars of decline, while other parts signal a mine returning to life.
That tension between what remains damaged and what is being rebuilt became the defining impression of Liberty Coal’ s media tour of Optimum Colliery.
Standing beneath conveyors and screening towers that still showed signs of age, the technical team walked us through the process. Run-of-mine coal is screened into different size fractions before entering either drum or cyclone circuits, where magnetite is used to separate coal from waste based on density. The explanation was very technical, but a plant manager gestured toward the weathered structures around us.“ I’ m focusing on making it work before we can make it look nice.” That sentence captured the reality of the site better than any corporate presentation could. The plant remains visibly unfinished, but most of the engineering work is underway.
At the time( July), the company stated that main commissioning was targeted for end-August 2026, with coal expected through the plant by end-September and nameplate capacity targeted for October. Initial throughput is expected to be 250 000 – 300 000 tonnes per month per module. The company is also planning water-management upgrades, including a future filter-press installation aimed at improving water recovery and reducing losses to slurry ponds.
Optimum is not an ordinary coal mine. Once part of Glencore’ s South African coal portfolio, the operation later became entangled in business rescue proceedings and ownership turmoil, drawing national attention. Liberty Coal acquired the operation and has since consolidated the various mining areas under a single mining right registered in the name of Liberty Investment Holdings.
The company invited media and industry stakeholders to tour the site ahead of a regional business and investment gathering in Middelburg, presenting the visit as an opportunity to see the progress made since taking ownership.
All images supplied by Liberty Coal
The dragline at Liberty Coal’ s Kwagga operations.
Background image supplied by Liberty Coal
“ Not everything is back, but there’ s definitely progress,” one Liberty Coal representative acknowledged during the tour, a comment that accurately reflected what was visible across the property. According to the company, the workforce has grown from roughly 400 – 500 people during care-and-maintenance to close to 2 000 employees and contractors as operations ramp up.
The tour focused on four major recapitalisation projects: the workshop complex, the heavy media separation( HMS) plant, the rail siding and the dragline operation. The HMS plant, a large blue processing facility that dominates part of the site, is central to the company’ s recovery strategy. Company representatives explained that much of the plant had previously been stripped of cables and equipment and was now being refurbished in stages.
If the HMS plant represents the technical heart of the operation, the rail siding is where the recovery becomes measurable. Stockpiles are divided into eight sections, allowing coal quality to be managed in parcels of roughly 1 000 tonnes before loading. The company operates under a strict four-hour train-loading turnaround, coordinating coal grades with Richards Bay Coal Terminal( RBCT) to ensure each train is directed to the correct export stream.
Currently, it exports RB2, RB3 and RB4 coal grades and is meeting its allocated export volumes. A recommissioned silo with a capacity of about 10 000 tonnes is expected to reduce train-loading times and increase siding capacity from roughly 12 trains per week to 15 trains per week.