PROSPECTING LICENCES RENEWED FOR MOLOPO FARMS PROJECT
FORTUNA DELIVERS ROBUST FEASIBILITY STUDY FOR THE DIAMBA PROJECT
• PROJECTS AND EXPLORATION
Image by Natanaelginting on Magnific. com
Image by Natanaelginting on Magnific. com
PROSPECTING LICENCES RENEWED FOR MOLOPO FARMS PROJECT
Location: Botswana Phase: Exploration Resource: Nickel
Drilling has begun at the Molopo Farms Project based in Botswana. Power Metal Resources confirmed that the prospecting licences have been renewed for the project. It is currently targeting a districtscale nickel and platinum group element discovery.
The London-listed exploration company’ s CEO, Sean Wade, said,“ I am very pleased to provide this update on the renewal of our licences and the upcoming drilling campaign. We remain completely committed to the project and are optimistic that this campaign will build on the significant body of work that has already taken place there and that a district-scale discovery remains within our reach. I look forward to further updating shareholders in the coming months.”
Highlights:
• The project ' s Prospecting Licence( PL) 311 / 2016 has been extended for a period of two years and is now valid until 31 March 2028.
• Drilling has commenced on a 1 600m programme of core drilling targeting an initial five high-interest geological and geophysical targets on the eastern feeder zone to the Molopo Farms Igneous Complex.
• Unlike previous and historical drilling, this programme will test targets within the controlling structure to the Molopo Farms Complex and its related feeder dykes.
• Drill siting is based on the latest interpretations of magnetic, AMT and TDEM data previously acquired by Power Metal, plus limited additional ground magnetic traverses.
• The programme will be results-driven and may be optimised as more data is acquired.
Power Metal interest Power Metal holds an 87.71 % interest in Kalahari Key Mineral Exploration( Pty) Ltd, a Botswana private company, which holds a 100 % interest in the Molopo Farms Complex Project.
Source: supplied by Power Metal Resources Plc
FORTUNA DELIVERS ROBUST FEASIBILITY STUDY FOR THE DIAMBA PROJECT
Location: Senegal Phase: Development Resource: Gold
The Diamba Sud Gold Project in Senegal, analysed at a USD3 500 / oz gold price, demonstrates high profitability with a 60 % after-tax IRR and a USD1-billion NPV 5 %. These robust metrics derived from a feasibility study indicate substantial value creation and the project ' s capacity to withstand cost fluctuations, despite the bullish price assumption.
Fortuna Mining Corporation announced positive results from the feasibility study for the project confirming an economically robust open-pit conventional carbon-in-leach( CIL) gold mine and advancing one of Fortuna’ s key growth opportunities.
Jorge A Ganoza, president and CEO of the company, commented,“ Diamba Sud is a standout growth project with high returns, fast payback and is expected to be our lowest-cost mine. Together with our Séguéla mine expansion, Diamba Sud supports our plan to grow our annual gold production rate by approximately 60 % to more than 500 000 ounces in 2028.” Ganoza concluded,“ With the
recent receipt of the environmental decree from the Senegalese government and the feasibility study complete, we are ready to move Diamba Sud toward a final investment decision upon completion of the mining permit process.”
Feasibility study highlights
Financial
• After-tax NPV5 % of USD1-billion, IRR of 60 %, and 1-year payback at USD3 500 / oz gold.
• At USD4 000 / oz gold, returns increase to NPV5 % of USD1.3- billion, IRR of 72 %, and 11-month payback.
Production and cost
• Strong first 4 years: Average annual gold production of 158 000 ounces.
• 9.4-year life of mine( LOM) with an average annual gold production of 116 000 ounces.
• Low-cost profile: Average AISC1 of USD1 056 / oz over the first 4 years and USD1 332 / oz over LOM.